10.
Pour the concrete inside the hole.
Reinforced Cement Concrete (minimum
30N/mm
2
at 28 days).
11.
During the concrete pouring, review
the levelling of the template with the
bolts and the lifting direction.
12.
Finish pouring the concrete until it
has reached the mark in the bolts
(185mm of the bolt out of the concrete)
and vibrate the concrete.
13.
Review the levelling and the
alineation of the bolts.
In case the top surface
finishing is good, 160mm of
the bolt out of the
concrete.