 Solar Inverter | Installer Manual                                                                                              [19] 

 

5.9  Inverter Start-Up 

Please refer to the following steps to start-up the inverter: 

a) 

Ensure device is securely fixed on the wall. 

b) 

Make sure all DC breakers and AC breakers are disconnected. 

c) 

Ensure AC cable is connected to the grid correctly. 

d) 

Ensure all PV panels are connected to the inverter correctly - DC connectors that are not used should be sealed by 

a cover. 

e) 

Turn on the external AC and DC connectors. 

f) 

Turn the DC switch to the “ON” position (if equipped with DC switch on the inverter). 

 

If the LED is not green, please check the following: 

All the connections are correct. 

All the external disconnect switches are closed. 

The DC switch of the inverter is in the “ON” position. 

 

 

 

 

Note! 

When starting the inverter for the first time, the country code will be set by default to the local settings. 

Please check that the country code is correct for your region. 

Set the time on the inverter using the button or by using the respective digital touchpoint e.g. LCD panel, 

touch key, iOS App, Android App, or desktop web portal. 

 

Below are the three possible inverter states indicating that the inverter has started up successfully: 

Waiting:

 Inverter is waiting to check the DC input voltage from panels is greater than 80V (lowest start-up voltage) but less 

than 120V (lowest operating voltage), display will indicate the Waiting status and green LED will flash. 

Checking:

 Inverter will check DC input environment automatically when DC input voltage from the PV panels exceeds 

120V and PV panels have enough energy to start inverter, display will indicate the Checking status and green LED will 

flash. 

Normal:

 Inverter begins to operate normally with green light on. Meanwhile feedback energy to grid, LCD displays present 

output power. 

 

 

 

 

Note! 

You can go to the setting interface on the display to follow the instructions if it is the first time to start up. 

 

 

Complete inverter Start-up guide

 

After the initial start-up the inverter, the display will revert to the language settings page. Short press to switch languages 

and long press to confirm selection. Once language has been set, the display will guide to set the safety regulation. Short 

press to switch safety regulation, and long press to confirm selection. 

 

 

 

 

Note! 

Please set-up the inverter if it is the first time to start-up. The above steps are for the regular start-up of 

the inverter. If it is the first time to start up the inverter, you need to carry-out the initial set-up of the 

inverter. 

Содержание Force 3.6S

Страница 1: ...________________________________ Energizer Solar Inverter Installer Manual 0 INSTALLER MANUAL This guide describes how to use and install Energizer Solar Inverters To prevent improper operation before...

Страница 2: ...3 4 Dimensions 6 4 Technical Data 7 4 1 DC Input 7 4 2 AC Output 7 4 3 Efficiency Protection and Standard 8 4 4 General Data 8 5 Installation 9 5 1 Packing List 9 5 2 Preparation 9 5 3 Installation S...

Страница 3: ...echnicians only 1 3 Symbols Used The following types of safety instructions and general information that appear in this document are as described below Danger Danger indicates a hazardous situation wh...

Страница 4: ...d operation may lead to serious safety and shock hazards or equipment damage Before connecting the inverter to the power distribution grid contact the local power distribution grid company to get appr...

Страница 5: ...nts to limit the current in grounding conductors for the safety The default value for higher speed personal protection is 30mA and 300mA per unit for lower speed fire safety Installation and Selection...

Страница 6: ...ter and the meter distribution system SPD test impulse D1 for signal line according to EN 61632 1 All DC cables should be installed to provide as short a run as possible and positive and negative cabl...

Страница 7: ...minals Introduction Item Description A DC Connector B DC Connector C DC Switch Optional D Waterproof Lock Valve E Communication Port F USB Port For Upgrade G WiFi GPRS LAN Optional H AC Connector I Gr...

Страница 8: ...Current input A input B A 15 15 MPPT Voltage Range Vdc 80 550 80 550 80 550 80 550 80 550 Start up Voltage V 120 120 120 120 120 No of MPP Trackers 2 2 2 2 2 Strings Per MPP Tracker 1 1 1 1 1 4 2 AC...

Страница 9: ...lf Consumption night W 1W Monitoring Module optional External WIFI Lan GPRS optional Communication Meter CT DRM USB update RS485 Display LCD Panel Touch Key iOS App Android App Web Portal Warranty 10...

Страница 10: ...up during installation and operation To avoid overheating always make sure the air flow around the inverter is not blocked Do not install in places where gas or flammable substances may be present Avo...

Страница 11: ...t set 8mm Crimping pliers Stripping pliers Screwdriver 5 5 Installation Steps Step 1 Fix the bracket on the wall Choose the wall location you want to install the inverter Place the bracket on the wall...

Страница 12: ...strings of PV modules Please select suitable PV modules with high reliability and quality Open circuit voltage of module array connected should be less than 600V and operating voltage should be withi...

Страница 13: ...d ensure all conductor strands are captured in the pin contact Crimp pin contact by using a crimping plier Put the pin contact with striped cable into the corresponding crimping pliers and crimp the c...

Страница 14: ...tion device is referred to the table above any load SHOULD NOT be connected with the inverter directly Step 3 AC Wiring Check the grid voltage and compare with the permitted voltage range refer to tec...

Страница 15: ...e bayonet out of the slot with a small screwdriver or the unlock tool and pull it out or unscrew the threaded sleeve then pull it out 5 7 Earth Connection Screw the ground screw with screwdriver as sh...

Страница 16: ...iFi GPRS port at the bottom of the inverter 4 For WiFi device Connect the WiFi with the local router and complete the WiFi configuration please refer to the WiFi product manual for more details 5 Set...

Страница 17: ...g devices Meter optional The inverter has integrated export limitation functionality To use this function a power meter or a CT must be installed For Meter installation please install it on the grid s...

Страница 18: ...se refer to following steps a Please contact our service support team to get the latest firmware and copy the files to U disk using the following file path Master Update master xxxxx_Master_Vx xx hex...

Страница 19: ...fault code Isolation fault will be displayed on the inverter screen and the RED LED indicator will light up Reactive Power Regulation for Voltage Variation Volt VAr Mode Details of how to enable this...

Страница 20: ...possible inverter states indicating that the inverter has started up successfully Waiting Inverter is waiting to check the DC input voltage from panels is greater than 80V lowest start up voltage but...

Страница 21: ...Inverter Switch Off Please follow the below steps to switch off the inverter a Switch off the inverter AC isolation switch b Switch off the DC isolation switch and allow 5 minutes for the inverter to...

Страница 22: ...________________________________________________________________________________________________________ Energizer Solar Inverter Installer Manual 21 6 2 Function Tree...

Страница 23: ...V with DC After the LCD switches off reconnect and check again EEPROM Fault Disconnect PV PV with DC After the LCD switches off reconnect and check again GFC Fault Disconnect DC and AC connector check...

Страница 24: ...OCP Turn off the PV and grid reconnect them PLL Fault System will reconnect if the utility is back to normal PV OVP Check the panel s open circuit voltage whether the value is similar or already 550Vd...

Страница 25: ...dy including a description of your system installation the model and serial number and any issues and troubleshooting you have already attempted 7 3 Routine Maintenance Safety check A safety check sho...

Страница 26: ...ckaging If it is no longer available you can use an equivalent box that meets the following requirements Suitable for loads more than 30 kg Contains a handle Can be fully closed 8 3 Storage and Transp...

Страница 27: ...Email hello energizersolar com Website www energizersolar com 2021 Energizer Energizer and certain graphic designs are trademarks of Energizer Brands LLC and related subsidiaries and are used under li...

Отзывы: