________________________________________________________________________________________________________
Energizer
Solar Inverter | Installer Manual [19]
5.9 Inverter Start-Up
Please refer to the following steps to start-up the inverter:
a)
Ensure device is securely fixed on the wall.
b)
Make sure all DC breakers and AC breakers are disconnected.
c)
Ensure AC cable is connected to the grid correctly.
d)
Ensure all PV panels are connected to the inverter correctly - DC connectors that are not used should be sealed by
a cover.
e)
Turn on the external AC and DC connectors.
f)
Turn the DC switch to the “ON” position (if equipped with DC switch on the inverter).
If the LED is not green, please check the following:
-
All the connections are correct.
-
All the external disconnect switches are closed.
-
The DC switch of the inverter is in the “ON” position.
Note!
When starting the inverter for the first time, the country code will be set by default to the local settings.
Please check that the country code is correct for your region.
Set the time on the inverter using the button or by using the respective digital touchpoint e.g. LCD panel,
touch key, iOS App, Android App, or desktop web portal.
Below are the three possible inverter states indicating that the inverter has started up successfully:
Waiting:
Inverter is waiting to check the DC input voltage from panels is greater than 80V (lowest start-up voltage) but less
than 120V (lowest operating voltage), display will indicate the Waiting status and green LED will flash.
Checking:
Inverter will check DC input environment automatically when DC input voltage from the PV panels exceeds
120V and PV panels have enough energy to start inverter, display will indicate the Checking status and green LED will
flash.
Normal:
Inverter begins to operate normally with green light on. Meanwhile feedback energy to grid, LCD displays present
output power.
Note!
You can go to the setting interface on the display to follow the instructions if it is the first time to start up.
•
Complete inverter Start-up guide
After the initial start-up the inverter, the display will revert to the language settings page. Short press to switch languages
and long press to confirm selection. Once language has been set, the display will guide to set the safety regulation. Short
press to switch safety regulation, and long press to confirm selection.
Note!
Please set-up the inverter if it is the first time to start-up. The above steps are for the regular start-up of
the inverter. If it is the first time to start up the inverter, you need to carry-out the initial set-up of the
inverter.