NetSure
™
-48 VDC Power System
Installation Instructions, IM582127000100 (Revision A, January 9, 2017)
Spec. No: 582127000100, 582127000103
Document Code: IM582127000100
Model No: 7100
Revision A, January 9, 2017
[1]
Customer Documentation Package
This document (IM582127000100) provides
Installation
Instructions
for NetSure™ -48 VDC Power System Model 7100,
Spec. No. 582127000, List 100 and List 103 only.
The complete Customer Documentation Package for List 100 and
List 103 consists of…
NetSure
™
-48 VDC Power System Installation Manual
•
Power System Installation Instructions:
IM582127000100
NetSure
™
-48 VDC Power System User Manual
•
Power System User Instructions: UM582127000100
NetSure
™
NCU Controller User Manual
•
NCU Controller User Instructions: UM1M830BNA
USB Drive with All Customer Documentation for 582127000
Applicable documents for this system are as follows.
•
Power System Installation Instructions:
IM582127000100 (instructions for List 100 and List 103)
•
Power System User Instructions: UM582127000100
(instructions for List 100 and List 103)
•
NCU Controller User Instructions: UM1M830BNA
•
Rectifier Instructions: UM1R482000e3
•
Converter Instructions: UM1C48241500
•
Power System “System Application Guide”:
SAG582127000
•
Engineering Drawings
•
Also provided on the USB drive is a controller
configuration drawing and the controller configuration
files loaded into the controller as shipped.
Installation Acceptance Checklist
Provided in this section is an Installation Acceptance Checklist.
This checklist helps ensure proper installation and initial operation
of the system. As the procedures presented in this document are
completed, check the appropriate box on this list. If the procedure
is not required to be performed for your installation site, also
check the box in this list to indicate that the procedure was read.
When installation is done, ensure that each block in this list has
been checked. Some of these procedures may have been factory
performed for you.
NOTE: The system is not powered up until the end of this
checklist.
NOTE: Some of these procedures may have been
performed at the factory for you.
Installing the System
Relay Rack Secured to Floor
Optional Battery Tray Installed
Optional Battery Tray Battery Disconnect Circuit Breaker
Installed
Optional Lug Adapter Busbar Kits Installed
Circuit Breakers Installed
Fuses Installed
Setting Jumper and Switch Options
Jumper on System Interface Board Set
Factory Switch Setting on IB2 Interface Board Verified
Factory Switch Setting on Optional EIB Interface Board
Verified
Making Electrical Connections
Relay Rack Frame Ground Connection Made
Central Office Ground Connection Made
AC Input and AC Input Equipment Grounding
Connections Made
External Alarm, Reference, Monitoring, and Control
Connections Made
Ethernet Connection Made
Load Connections Made
Battery Connections Made
Batteries Installed and Connected in the Battery Trays (if
furnished)
Installing the Modules
Rectifier and Converter Modules Installed
Initially Starting the System
System Started, Configured, and Checked
StockCheck.com