12 Chapter 2 Single UPS Installation And Commissioning
Liebert
®
ITA 16kVA And 20kVA UPS User Manual
Installation
hole (6 pcs)
Left guide rail
Right guide rail
Figure 2-7 Appearance of the guide rail
Distinguish the guide rail screw and the panel screw according to Figure 2-8.
Guide rail screw
Panel screw
Figure 2-8 Appearance of the screw
2) Adjust the length of the guide rail according to the dimensions of the rack.
3) Align the installation holes of the guide rail with the square holes of the rack, fix the guide rail onto the rack through
the guide rail screws (a total of eight), each left guide rail and right guide rail need four guide rail screws, as shown in
Figure 2-9.
Guide rail screw (4 pcs)
Guide rail
Guide rail holder
Square hole
Figure 2-9 Installing the guide rail
Note
1. The guide rail holder must be close to the front of the rack.
2. Any end of one guide rail has six installation holes (see Figure 2-7), do not use the two installation holes in the middle when
fixing the guide rail. It is recommended to use the top and bottom installation hole (from top to bottom, installation hole 1 and
installation hole 6).
The guide rail installation is finished, as shown in Figure 2-10.