Chapter 2 Single UPS Installation And Commissioning 11
Liebert
®
ITA 16kVA And 20kVA UPS User Manual
Support base
Support base extension
Fastening
Figure 2-4 Connecting the support base with support base extension
3. Place the UPS on the support bases and support base extensions, as shown in Figure 2-5.
UPS
Support base
Support base
UPS
Battery
module (4 pcs)
Support
base
Support
base
Figure 2-5 UPS and battery module Installation complete
2.4.2 Rack Installation
Installation procedures for UPS
1. Use eight M4 × 10 screws to fix two brackets (accessories) respectively on both sides of the UPS front panel, as
shown in Figure 2-6.
Figure 2-6 Installing brackets
Note
It is prohibited to move the UPS through the brackets.
2. Install the guide rails.
You need to use guide rails when you select Liebert
®
ITA series UPS and its options, and select the rack installation.
The installation procedures of the guide rails are as follows:
1) Take out the guide rails (one left guide rail and one right guide rail), guide rail screws and panel screws from the
package, distinguish the left guide rail and right guide rail according to Figure 2-7, and confirm its retractable function
respectively.