42
EL250RT
4 CABLE PIT ASSEMBLY AND POSITIONING
Elkron supplies a dedicated cable pit for fixing the infrared columns in place (reference
PO/DT250
). For assembly and
positioning, follow the steps described below.
1.
Unite the edge highlighted in the figure with the recess in the other panel and fix them with the screws
2.
Insert the third side in the same way and tighten
the screws
3.
Pull the two opposite panels slightly apart to insert
the last side of the cable pit
4.
Insert and fully tighten all the remaining screws.