5. Start & Stop
5.1 Start the Inverter
To start up the Inverter, it is important that the following steps are strictly followed:
1.
Switch the grid supply main Switch (AC) ON first.
2.
Switch the DC switch ON. If the voltage of PV arrays are higher than start up voltage,
the inverter will turn on. The LED status indicator will light.
3.
When both the DC and the AC sides supply to the inverter, it will be ready to generate
power. Initially, the inverter will check both its internal parameters and the parameters of
the AC grid, to ensure that they are within the acceptable limits. At the same time, the
green LED will flash and the LCD displays the information of INITIALIZING.
4.
After 60-300 seconds (depending on local requirement), the inverter will start to generate
power. The green LED will be on continually and the LCD displays GENERATING.
WARNING:
Do not touch the surface when the inverter is operating. It may be hotand
cause burns.
5.2 Stop the Inverter
To stop the Inverter, the following steps must be strictly followed:
1. Switch the Supply Main Switch (AC) OFF.
2. Wait 30 seconds. Switch the DC Switch OFF. All the LEDs of the inverter will be off in
one minute.