12
Installation, Operation, And Service Instructions
8.
COMBINATION HEATING/COOLING SYSTEM WITH CHILLED WATER
The chiller must be piped in parallel with the boiler and isolation valves installed to
prevent the chilled water from circulating through the boiler and heated water from
circulating through the chiller. See Figure 25.
Figure 25.
9.
SINGLE BOILER PIPING WITH BLEND PUMP
When burner is operating the water flow throughout the boiler shall be not less than
1.8 GPM for each 100,000 BTU/HR of gross boiler output. Size blend pump
accordingly. See Table 3
Blend Pump
Primary/Secondary
Pump
Boiler Model
GPM
GPM
OWB-9
OWB-15
OWB-25
OWB-35 16.3
78.9
OWB-50 19.6
94.9
Maximum water flow resistance for boilers is 14” w.c
Table 3.
S
R
Circulating Pumps
Cold Water Feed
Flow Check
Drain Cock
Supply to System
Return from System
Insulation Valve # 4
Chiller
Insulation
Valve # 4
Insulation Valve # 3
Note:
1.
When in cooling mode isolation valves 1 and 2 must be closed and valves 3 and 4 open.
2.
When in heating mode isolation valves 1 and 2 must be open and valves 3 and 4 closed.