8. Commissioning
After completing the inspection, turn on all BESS switches in turn and energize the AC circuit from
the power grid to check whether BESS can operate normally without fault.
Bess power on process
Picture 8-1 Bess power on process
Auxiliary circuit power on process
Picture 8-2 Power on process of auxiliary circuit
Power on process of main circuit
Open the
auxiliary circuit
MCB
Open main
circuit breaker
Close cabinet
door
Turn on the total
secondary power
supply MCB
Turn on the air
conditioner MCB
Close the button of the
intearated box
/ecoess.co.uk
Mobile : + 44 (0) 7729636318
Landline : + 44 (0)116 366 9980
Website : www.ecoess.co.uk
E-mail : [email protected]
72- Evington Road,
LE2 1HH Leicester, UK
Ensure that all bolts are tightened according to the following requirements. After confirming the torque,
make red marks on the bolts as identification.
Item
No
Type
Position
Fixed part
Specified value
1 Outdoor
energy
Outdoor energy storage cabinet
and ground fixing
M12 * 150
96±5N·m
2
AC, load, PV cable
M8 * 16
10±1N·m