Eclipse BoostPak Leak Detection Option, V3, Installation Guide 630-LD 7/30/2010

Operation

Preliminary

This section supplements the operation section in your
Installation Guide 630.

Leak Detector Operation

When power is applied, the methane sensor will go to a
warmup mode for about 5 minutes.

The green LED indicates normal operation. The yellow
LED indicates a system failure. If this situation occurs, you
should contact the leak detector manufacturer for further
assistance. The detector has 2 sensors. A CO sensor
located in the module has no control panel function. The
remote sensor for methane operates relays in the control
panel. The four red LEDs indicate the gas concentration
reaches alarm level A and B for both sensors.

When the methane concentration reaches the first alarm
level (Alarm A), panel relay CR127 changes state. If the
gas concentration reaches the second alarm level (Alarm
B), panel relay CR128 changes state and the audible
alarm comes on.

Annunciation Control Panel Operation

On initial application of power from the building circuit
breaker panel, the yellow light on the Close Gas Valve
push button will come on. When the detector module
determines a safe condition, the green Safe to Enter light
comes on. Then the Open Gas Valve push button can be
pressed to allow gas supply to the equipment room. The
button must be held until its green light comes on.

If the gas concentration gets to the second alarm level,
then the gas valve will shut and the red Leak Detected
light and Alarm.

3

Содержание BoostPak

Страница 1: ...Eclipse BoostPak Leak Detection Option 630 LD Install Guide 7 30 2010 Version 3 ...

Страница 2: ... and Eclipse will not be liable for any other injury loss damage or expenses whether direct or consequential including but not limited to loss of use income or damage to material arising in connection with the sale installation use of inability to use or the repair or replacement of Eclipse s products Any operation expressly prohibited in this manual any adjustment or assembly procedures not recom...

Страница 3: ... result Never try to operate a BoostPak if it shows signs of damage or malfunction This manual provides information in the use of the BoostPak for its specific design purpose Do not deviate from any instructions or application limits described herein without written advice from Eclipse Capabilities Only qualified personnel with good mechanical aptitude and experience with combustion equipment shou...

Страница 4: ...t room at eye level The panel must be secured to the wall and conduits to it must be separately supported The panel will need 3 conduit entrances 120VAC power supply from building circuit breaker 3 wires sized to handle 10 amps plus additional loads connected to the alarm terminals 120VAC power and switch signal to gas valve 3 wires not smaller than 18 gauge as determined by local codes 120VAC pow...

Страница 5: ... of the gas valve If a direct connection is needed it can be wired in series with the run interlocks or in series with the low inlet gas switch When connected to the run interlocks a leak detect will provide a normal shutdown of the BoostPak refer to the appropriate installation guide When connected to the low inlet gas a leak detect will result in an alarm condition shutdown Checklist After Insta...

Страница 6: ... at first and second alarm points Commissioning Record Nameplate Information Leak Detect Module Serial Number ___________ Annunciation Control Panel Serial Number ___________ Mechanical Installation Ambient Temperature ___________ Panel Mounting Secure Rigid Level ___________ Conduit Properly Supported ___________ Proper and Adequate Detector Location ___________ Leak Detector Performance Alarm A ...

Страница 7: ... indicate the gas concentration reaches alarm level A and B for both sensors When the methane concentration reaches the first alarm level Alarm A panel relay CR127 changes state If the gas concentration reaches the second alarm level Alarm B panel relay CR128 changes state and the audible alarm comes on Annunciation Control Panel Operation On initial application of power from the building circuit ...

Страница 8: ...pond properly return to the manufacturer for repair If field adjustments are required the optional display is needed Flow a span gas at the recommended rate and observe the action of the LEDs and outputs Span gas can be purchased through your local industrial gas supplier Troubleshooting Guide Problem Possible Cause Solution No lights at annunciation panel Power supply to panel disconnected not po...

Страница 9: ...9 Eclipse BoostPak Leak Detection Option V3 Installation Guide 630 LD 7 30 2010 Panel Layout Enclosure and Terminal Strip Enclosure 14 H x 12 W x 6 D 10 40 30 20 Panel 12 75 H x 10 88 W ...

Страница 10: ...rminal on device Panel ground lug Used for indexing to sheet X and line Y KEY CUSTOMER SUPPLIED LEAK DETECT ENCLOSURE TERMINALS ARE NOT SHOWN IN CORRECT ORDER AND ARE FOR REFERENCE ONLY ON THIS DWG SEE PANEL LAYOUT DWG FOR TB1 TERMINAL STRIP LAYOUT REMOTE COMBUSTIBLE GAS SENSOR SHIELD 125GLD 118FAN SWITCH PROOF OF CLOSURE POSITION SWITCH OPEN POSITION 108SOL SSOV COMM COMM NC NO G Item Number Ecli...

Страница 11: ...ter mm inch in 3 94 x 10 2 MJ Nm Btu ft standard 26 86 From To Multiply By kiloPascals kPa millibar mbar 10 meter m millimeter mm 1000 millibar mbar kiloPascals kPa 0 1 millimeter mm meter m 0 001 From To Multiply By actual cubic foot h acfh actual cubic meter h am h 2 832 x 10 2 standard cubic foot h scfh normal cubic meter h Nm h 2 629 x 10 2 degrees Fahrenheit F degrees Celsius C F 32 x 5 9 pou...

Страница 12: ...Installation Manual 630 LD 7 30 10 ...

Отзывы: