The general stages described in the following table, listed in the required order of execution.
Table
4-1: Outline of typical NPT-1020 equipment installation sequence
Step
Procedure
1
Install a rack (if required)
2
Unpack and perform a visual inspection
3
Install ancillary equipment in the rack, including:
RAP unit
FST (optional)
Optional ODF units
Optional DDF units
Optional SM_10E ICP units
4
Install the NPT-1020 shelf in the rack
5
Install the Dslot modules in the NPT-1020 shelf (if required)
6
Install the SFP modules in the NPT-1020 shelf
7
Install the EXT-2U shelf in the rack (if required)
8
Install the power module in the EXT-2U shelf
9
Install extension cards in the EXT-2U shelf
10
Route and connect all cables and fibers, including:
Power and alarm cables
Optical fibers to optical modules transceivers
Traffic cables to electrical cards
Data cables
Timing cables
Management cable
Orderwire cable
PCM interface cables
4.4
Unpacking and Performing Visual Inspection
Before you start:
Before unpacking, make a preliminary inspection of the shipping boxes. Immediately report evidence of
damage to the carrier, the project manager, and your local ECI representative.