System Parallel Module

Chapter 3       Installation Plan and Unpacking

Use the following basic sequence of steps to install the System Parallel Module 

1.  Create an installation plan.

2.  Prepare your site for the SPM.

3.  Inspect and unpack the SPM.

4.  Unload and install the SPM, and wire the system.

5.  Complete the Installation Checklist.

6.  Have authorized service personnel perform preliminary operational checks and start up the system. 

3 .1 

Creating an Installation Plan

Before installing the SPM, read and understand how this manual applies to the system being installed. Use the 
procedures and illustrations in this section to create a logical plan for installing the SPM. This section contains 
the following information:

• 

Physical features and requirements, including dimensions

• 

Power wiring installation notes

• 

Location of conduit and wire entry landing plates

• 

Location of power terminals

Startup and operational checks for parallel systems or installations with accessory 
cabinets must be performed by an authorized Eaton Customer Service Engineer, or the 
warranty terms may become void. This service is offered as part of the sales contract for 
the UPS. Contact an Eaton service representative in advance (usually a two-week notice 
is required) to reserve a preferred startup date.

3 .2 

Preparing the Site

Similar with the UPS, the SPM installation site should meet the environmental parameters outlined in this 
manual. If the UPS is to be operated at an altitude higher than 1000m (3300 ft.), contact an Eaton service 
representative for important information about high altitude operation. The operating environment must meet 
the weight, clearance, and environmental requirements specified.

NOTE 

CAUTION

It must be ensured that no line input source can accidentally be connected to the SPM during the 
SPM installation.

WARNING

• 

Installation may only be carried out by qualified technicians and in conformity with the 
applicable safety standards.

• 

The SPM is not suitable for IT or corner-earthed power distribution systems.

Содержание SPM 120

Страница 1: ...System Parallel Module Installation and Operation Manual Eaton UPS Accessories...

Страница 2: ......

Страница 3: ...f the information contained in this manual but no liability can be accepted for any errors or omission The right to make design modifications is reserved IMPORTANT SAFETY INSTRUCTIONS SAVE THESE INSTR...

Страница 4: ...er Location 12 4 Installation 13 4 1 Preliminary Installation Information 13 4 2 Unloading the SPM Cabinet from the Pallet 13 4 3 External Power Cables Connecting 15 4 4 External Signaling Cables Conn...

Страница 5: ...BottomViews 7 Figure 3 3 SPM Cabinet as Shipped on Pallet wood container removed 12 Figure 3 4 Breaker Location 12 Figure 4 1 Removing the Front Shipping Bracket 14 Figure 4 2 Attaching the Ramp to t...

Страница 6: ...List of Tables Table 3 1 SPM CabinetWeights 6 Table 3 2 SPM Cabinet Clearances 6 Table 3 3 External PowerWiring Requirements for EBCB 9...

Страница 7: ...SPM Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer or the warranty terms specified become void This service is offered as part of the sales contract...

Страница 8: ...PS systems in a 2 1 system 120kVA to allow 2x 120kVA UPS systems in a 1 1 system 600kVA to allow 4 x 200kVA UPS systems in a 3 1 system 400kVA to allow 3x 200kVA UPS systems in a 2 1 system 200kVA to...

Страница 9: ...g reuse or hazardous waste centre This symbol indicates that you should not discard waste electrical or electronic equipment WEEE in the trash For proper disposal contact your local recycling reuse or...

Страница 10: ...Accessory or UPS operation by any action that includes removal of the earth ground connection with loads attached Ensure all power is disconnected before performing installation or service ELECTRIC EN...

Страница 11: ...al checks for parallel systems or installations with accessory cabinets must be performed by an authorized Eaton Customer Service Engineer or the warranty terms may become void This service is offered...

Страница 12: ...s No special rear clearances required for the SPM other clearances around the SPM cabinet can follow the UPS The basic environmental requirements for operation of the UPS and Accessories are AmbientTe...

Страница 13: ...Right and Rear Views Dimensions are in millimetres inches FrontView RightView RearView TopView BottomView Dimensions are in millimetres inches Figure 3 2 SPM Cabinet Dimensions Top and Bottom Views Ca...

Страница 14: ...h for UPS cabinet conduit and terminal specifications and locations The term line up and match refers to accessory cabinets that are physically located adjacent to the UPS The term standalone refers t...

Страница 15: ...M16 Hex L3 240 1 M16 Bolt Mounting 210 23 71 M16 Hex N 240 1 M16 Bolt Mounting 210 23 71 M16 Hex The UPS to SPM MOB L1 70 1 M16 Bolt Mounting 210 23 71 M16 Hex L2 70 1 M16 Bolt Mounting 210 23 71 M16...

Страница 16: ...Bolt Mounting 210 23 71 M16 Hex L3 630 1 M16 Bolt Mounting 210 23 71 M16 Hex N 630 1 M16 Bolt Mounting 210 23 71 M16 Hex The UPS to SPM MOB L1 150 1 M16 Bolt Mounting 210 23 71 M16 Hex L2 150 1 M16 B...

Страница 17: ...ackets and ramp extension packed at the top of the cabinet a Straighten the tabs securing the top panel of the wooden container to the side panels of the container b Remove the top panel and retain fo...

Страница 18: ...ner 6 Inspect the contents for any evidence of physical damage and compare each item with the Bill of Lading If damage has occurred or shortages are evident contact an Eaton service representative imm...

Страница 19: ...ace the ramp against the front of the pallet c Attach the ramp extension to the front of the ramp by inserting the tabs on the extension into the slots at the bottom of the ramp 4 If the leveling feet...

Страница 20: ...vel 10 If permanently mounting the system proceed to Step 11 11 Using the retained hardware reinstall the shipping brackets removed in Step 2 and Step 5 to the front and rear of the UPS cabinet with t...

Страница 21: ...n and terminal locations See paragraph 3 2 2 Table 3 3 for wiring and termination requirements The utility source must be the same as the UPS bypass input 5 Route and Connect the power cables L1 L2 L3...

Страница 22: ...To Utility Connections L2 To Utility Connections N To Utility Connections L3 To Utility Connections L1 To UPS1 Output N To UPS2 Output N To UPS3 Output N To UPS4 Output N To UPS1 Output L1 To UPS2 Out...

Страница 23: ...N7 To UPS2 Interface CN7 To UPS2 Interface CN7 To UPS1 Interface CN7 To UPS1 Interface CN7 To UPS4 Building Alarm2 To UPS4 Building Alarm2 To UPS3 Building Alarm2 To UPS3 Building Alarm2 To UPS2 Build...

Страница 24: ...r must verify the operation of the UPS system and commission it to support the critical load The service representative cannot perform any installation tasks other than verifying software and operatin...

Страница 25: ...19 System Parallel Module Notes...

Страница 26: ...Card Slot 2 ALARM INPUTS Input1 Communications Panel 1 2 Input2 3 4 Input3 5 6 EPO NC 1 2 NO 3 4 Pull Chain 1 2 PARALLEL SIGNALS RJ45 RJ45 CAN IN CAN OUT Card Slot 1 Card Slot 2 ALARM INPUTS Input1 Co...

Страница 27: ...DAILY Maintenance 6 2 2 PERIODIC Maintenance 6 2 3 ANNUAL Maintenance 6 2 4 BATTERY Maintenance Perform the following steps daily 1 Check the area surrounding the UPS system Ensure the area is not clu...

Страница 28: ...MBS Amps 705 1173 Max current of MIS Amps 654 1086 Max current of MOB Amps 218 362 Operating Temperature 5 C 40 C Storage Temperature 25 C to 55 C Transit Temperature 25 C to 60 C Humidity 5 to 95 ma...

Страница 29: ......

Страница 30: ......

Страница 31: ......

Страница 32: ...614 01728 00...

Отзывы: