5.6.2 Battery Installation and Connection
The 40 batteries are divided into two groups connected in parallel for use. Each group has has 20 batteries in series
(BAT+, N and BAT-). Install the batteries starting at the bottom of the cabinet and working up one by one (Figures 5-54
and 5-55).
Figure 5-54: Front Internal View, Models BP240V40L and BP240V40L-NIB
Figure 5-55: Rear Internal View, Models BP240V40L and BP240V40L-NIB
5. Installation
Layer 3
Layer 4
Layer 2
Layer 1
Fuses, 250A (x4)
Battery Breaker
10-20 kVA Connector
25-50 kVA Connector
Battery Group 2
Battery Group 1
Positive Battery Group 2
Negative Battery Group 2
Positive Battery Group 1
Negative Battery Group 1
Содержание Smart Online S3M BP240V09
Страница 38: ...38 5 Installation Figure 5 32 Wiring Diagram for Installation of 80 Batteries ...
Страница 46: ...46 5 Installation Figure 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Страница 49: ...49 5 Installation Figure 5 44A 2 Remove top right side and left side plates Figure 5 44 ...
Страница 54: ...54 5 Installation 14 Reinstall the covers and the screws Figure 5 53 Figure 5 53 ...
Страница 113: ...113 5 Instalación Figura 5 32 Diagrama de Cableado para la Instalación de 80 Baterías ...
Страница 121: ...121 5 Instalación Figura 5 41C Frente Capa 3 Capa 2 Capa 1 Atrás ...
Страница 124: ...124 5 Instalación Figura 5 44A 2 Retire las placas superior lado derecho y lado izquierdo Figura 5 44 ...
Страница 129: ...129 5 Instalación 14 Reinstale las cubiertas y los tornillos Figura 5 53 Figura 5 53 ...
Страница 196: ...196 5 Installation Figure 5 41C Avant Couche 3 Couche 2 Couche 1 Arrière ...
Страница 199: ...199 5 Installation Figure 5 44A 2 Retirer les plaques du haut de droite et de gauche Figure 5 44 ...
Страница 204: ...204 5 Installation 14 Réinstaller les couvercles et les vis Figure 5 53 Figure 5 53 ...