6
Installation Guide
RE 2 Post Rack Assembly and Installation Guide Issue 1
Step - 5
Stand the rack up and square as shown in
Figure 3
.
Tighten all fixings to
12
Nm (tol/-
2
Nm)
Step - 6
The bottom angles need to be secured to the floor
(floor fixings not included)
Step - 7
If required, install the 2 Cable Basket / PDU brackets to
the RE 2 Post Rack vertical mounting rail side or, using
cage nuts, to the 19” rail.
Once secured to the floor the rack is now ready for
equipment installation.
SQUARE
Figure
-
3