12
Installation Guide
RE 2 Post Rack Assembly and Installation Guide Issue 1
6. RE 2 Post Rack Earth Bonding.
The RE 2 Post Rack vertical mounting rails have earth bonding
holes at both top and bottom. This enables easy earth bonding from
above or below.
Step - 1
1 serrated nut and bolt kit is supplied as standard
for the purpose of earth bonding (see Fig 1). Locate this nut
and bolt kit in the desired earth hole position and tighten
to12Nm.
Step - 2
Attach a pre-terminated earth wire to the bolt,
then the washer and nut and tighten to12Nm.
Fig 1
Rack Earth Stud position. Can
be re-positioned to top.