Eaton 9390 Guide Specification 

October 9, 2009 

 

 

 

D. 

To comply with agency safety requirements, the UPS module shall not rely upon any 
disconnect devices outside of the UPS module to isolate the battery cabinet from the 
UPS module. 

 

PART 3 - EXECUTION 

 
3.01 

INSTALLATION 

 

A. 

Install in accordance with manufacturer’s instructions. 

 
3.02 

COMMISSIONING 

 

A. 

Factory start-up shall be provided on a 5x8 basis (7 x 24 optional).  Start-up service shall 
be provided at no extra charge and shall include one visit to perform all procedures and 
tests specified within UPS Installation and Operation manual.  UPS manufacturer shall 
also offer the following optional services: 

1. 

Pre-energize visit to inspect installation and provide guidance to installers as 
required. 

2. 

Post-start-up visit for alarm notification configuration, operator training, generator 
testing, etc. 

 

B. 

The following procedures and tests shall be performed by Field Service personnel during 
the UPS startup: 

1. 

Visual Inspection: 

a) 

Visually inspect all equipment for signs of damage or foreign materials. 

b) 

Observe the type of ventilation, the cleanliness of the room, the use of 
proper signs, and any other safety related factors. 

2. 

Mechanical Inspection: 

a) 

Check all the power connections for tightness. 

b) 

Check all the control wiring terminations and plugs for tightness or proper 
seating. 

3. 

Electrical Pre-check: 

a) 

Check the DC bus for a possible short circuit. 

b) 

Check input and Bypass power for proper voltages and phase rotation. 

c) 

Check all lamp test functions. 

4. 

Initial UPS Startup: 

a) 

Verify that all the alarms are in a “go” condition. 

b) 

Energize the UPS module and verify the proper DC, walkup, and AC 
phase on. 

c) 

Check the DC link holding voltage, AC output voltages, and output 
waveforms. 

d) 

Check the final DC link voltage and Inverter AC output.  Adjust if 
required. 

e) 

Check for the proper synchronization. 

Содержание Powerware 9390

Страница 1: ...UPS Module shall operate as an on line fully automatic system in the following modes 1 Normal Utilizing commercial AC power the critical load shall be continuously supplied by the Inverter The Invert...

Страница 2: ...EC 62040 1 1 International Electrotechnical Commission Uninterruptible power systems UPS Part 1 1 General and safety requirements for UPS used in operator access areas E IEC 62040 1 2 International El...

Страница 3: ...f all field service offices must be submitted with the proposal Third party maintenance will not be accepted E Spare Parts Support Parts supplies shall be located in the field to provide 80 of all eme...

Страница 4: ...nts the IGBTs from sourcing current in excess of their published ratings 3 An option shall be provided to allow the rectifier to be capable of operating from a delta transformer output or high impedan...

Страница 5: ...onditions a Bypass voltage out of limits 10 of nominal b Bypass frequency out of limits 3 Hz adjustable factory set c Bypass out of synchronization d Bypass phase rotation installation error 6 Static...

Страница 6: ...ocations 1 Rectifier charger input connections 3 wire plus ground 2 Bypass input connections 3 wire plus ground for 3 wire plus ground output configuration 480Vac or 4 wire plus ground for 4 wire plus...

Страница 7: ...ll be removable from the front of the battery cabinet 4 Each battery cabinet shall feature a DC rated circuit breaker The circuit breaker within the battery cabinet shall only provide protection to th...

Страница 8: ...VAC 3 wire plus ground for 3 wire plus ground output configuration 2 Operating input voltage range 10 15 of average nominal input voltage without battery discharge 3 For 60Hz systems operating input f...

Страница 9: ...6 DC sensing Redundant DC voltage sensing methods shall be incorporated for providing battery over voltage protection 7 Battery charger characteristics The UPS battery charging system shall have the...

Страница 10: ...le 11 Phase angle control a Balanced linear load shall be 1 degree from nominal 120 degrees b Unbalanced linear loads shall less than 5 degrees from average phase voltage for 100 load unbalance 12 Pha...

Страница 11: ...e UPS shall withstand a 25 kV pulse without damage and with no disturbance or adverse effect to the critical load 11 Efficiency The UPS efficiency shall greater than 99 over the range of 10 to 100 loa...

Страница 12: ...cessor controlled circuitry The UPS controls shall have the following design and operating characteristics 1 Fully automatic operation of the UPS shall be provided through the use of microprocessor co...

Страница 13: ...tive cover which provides the following signals and communication features in a Class 2 environment 1 Alarm contact A dry contact for annunciating a summary alarm shall be provided for customer use Th...

Страница 14: ...attended sequential shutdown of one or multiple computers powered by one UPS This shutdown shall be performed via in network or out of network means The order of shutdown shall be user defined allowin...

Страница 15: ...ation operator training generator testing etc B The following procedures and tests shall be performed by Field Service personnel during the UPS startup 1 Visual Inspection a Visually inspect all equip...

Страница 16: ...g service with monthly reports for UPS and battery performance Standard response time shall be 8 hours from receipt of call Manufacturer shall also offer as an option 7x24 on site service support with...

Отзывы: