O & M Manual for the CHGENLC Automatic
Transfer Switch with ATC-100 Control
Figure 53. Location of the Service Entrance Cover Screws.
Step 4:
Open the new service entrance cover door and align it
with the holes in the ATS door.
Step 5:
Secure the new service entrance cover to the ATS door
using the hardware supplied.
Step 6:
Close the service entrance cover door.
Step 7:
Apply utility (Source 1) power and place the generator
control selector switch in the “AUTO” position after the
service entrance cover has been replaced. Test the sys-
tem for proper functionality.
7.5 Troubleshooting
Table 5 contains troubleshooting information for the CHGENLC
ATS. If a problem still exists after completing the troubleshooting
procedures, contact an authorized Eaton sales representative.
Table 5. Troubleshooting Chart
SCREWS
PROBLEM
CAUSE
CORRECTION
The automatic transfer switch does not transfer to the
generator.
1. The circuit breaker on the generator is open.
2. The generator voltage is not acceptable.
3. The generator breaker on the ATS unit is open (SE only option)
1. Reset the generator circuit breaker.
2. Refer to the generator User's Manual.
3. Turn “ON” the generator breaker on the ATS unit (SE only option)
The automatic transfer switch does not transfer to the
utility.
1. The service disconnect breaker is open.
2. The utility voltage is not acceptable.
1. Reset the service disconnect breaker.
2. Wait for the utility voltage to return to normal.
The generator is still running after the transfer switch
transfers to the utility.
Engine cool down period.
The engine should stop after the cool down period.