Eaton 9E UPS (20–30 kVA, 208/220V) Generation 3 Installation and Operation Manual P-164000301—Rev 1
www.eaton.com/powerquality
3-1
Chapter 3
UPS Installation Plan and Unpacking
Use the following basic sequence of steps to install the UPS:
1.
Create an installation plan for the UPS system (Chapter 3).
2.
Prepare your site for the UPS system (Chapter 3).
3.
Inspect and unpack the UPS cabinet (Chapter 3).
4.
Unload and install the UPS cabinet, and wire the system (Chapter 4).
5.
Install features, accessories, or options, as applicable (Chapter 4).
6.
Complete the Installation Checklist (Chapter 4).
7.
Have authorized service personnel perform preliminary operational checks and start up the system.
3.1
Creating an Installation Plan
Before installing the UPS system, read and understand how this manual applies to the system being installed.
Use the procedures and illustrations in paragraph 3.2 and Chapter 4 to create a logical plan for installing the
system.
3.2
Preparing the Site
For the UPS system to operate at peak efficiency, the installation site should meet the environmental
parameters outlined in this manual. The operating environment must meet the weight, clearance, and
environmental requirements specified.
3.2.1
Environmental and Installation Considerations
The UPS system installation must meet the following guidelines:
l
The system must be installed on a level floor suitable for computer or electronic equipment.
l
The system must be operated at an altitude no higher than 1500m (5000 ft) without derating. See Table 3-1
for altitude and thermal derating requirements. For additional assistance with high altitude operation,
contact an Eaton service representative (see paragraph 1.7).
l
The system must be installed in a temperature and humidity controlled indoor area free of conductive
contaminants.
Failure to follow guidelines may void your warranty.
NOTE 1
Startup may be performed by the customer’s battery qualified electrical contractor
for single (not parallel) UPS installations without any accessory cabinets such as an
External Battery Cabinet.
NOTE 2
Startup and operational checks for parallel systems or installations with accessory
cabinets must be performed by an authorized Eaton Customer Service Engineer, or
the warranty terms specified on page W-1 become void. This service is offered as
part of the sales contract for the UPS. Contact an Eaton service representative in
advance (usually a two-week notice is required) to reserve a preferred startup date.
Содержание 9E
Страница 1: ...Eaton 9E UPS 20 30 kVA 208 220V Generation 3 Installation and Operation Manual ...
Страница 2: ......
Страница 3: ...Eaton 9E UPS 20 30 kVA 208 220V Generation 3 Installation and Operation Manual ...
Страница 21: ...Section 1 Installation ...
Страница 22: ......
Страница 65: ...Section 2 Operation ...
Страница 66: ......
Страница 113: ......
Страница 114: ... P 164000301 1 P 164000301 1 ...