INSTALLATION INSTRUCTIONS
4.1 Preparations before installation
4.1.1 Space requirements.
Refer to 3.3 for the dimensions of the lift. There must also be a clearance of at least 1 meter between the lifting platform and fixed
elements (e.g. wall) in all lifting positions. There must be sufficient space at the ends of the lifting platform for driving vehicles on and off.
To stop vehicles colliding with the ceiling, it is advisable to fit an overhead light barrier in low ceiling buildings.
4.1.2 Foundations and connections
Only use this lift on a surface that is stable, level and dry and not slippery, and capable of sustaining the load.
This lift must be installed
on a solid level concrete floor with no more than 3-degrees of slope. Failure to do so could cause personal injury or death.
Do not install
or use the lift on any asphalt surface.
The user must have the following work performed before erecting the lift.
Construction of the foundation following consultation with the manufacturer’s customer service or an authorized service agent.
Routing of the wiring to the installation location. Refer also to the corresponding information on the name plate and in the operation
instructions. Before doing electrical connection, make sure the lift is electrically adapt to the local power supply.
The user must provide fuse protection for the connection. Requirements for power supply cable of the installation site: at least
2.5mm
2
wire core for 3Ph power and 4.0mm
2
wire core for 1Ph power.
Attention: electrical system connection must be done by licensed
technicians.
Routing of the compressed air connection to the installation location.
4.1.3 Foundations preparations
There must be a clearance of at least 1 meter between the lifting platform and fixed elements (e.g. wall) in all lifting positions.
There must also be sufficient space for driving vehicles on and off.
C25-C30 concrete foundation with a minimum thickness of 150mm.
Surface: Horizontal and even (Gradients max. 0.5 %).
Newly built concrete ground must be older than 20days.
4.1.4 Tools and equipment needed for installation
Tool name
Specification
Qty
Electrical drill (Only necessary to fixed installation )
With D12 drill bit.
1
Open spanner
D17-19mm
2
Cross socket screw driver
PH2
1
Socket spanner
D24mm
1
Lifting equipment
Capacity 1000kg
1
4.1.5 Checking parts
Unfold the package and check if any parts missed as per the following list. Do not hesitate to contact us in case any parts missed, but if you
do not contact us and insist installing upon the lack of some parts, we as well as our dealers will not bear any responsibility for this and will
charge for any parts subsequently demanded by the buyer.