pouring.

 Concrete ballast should be 

cast in-place around the tank 

in the excavation (Figure 3). 

Alternatively, pre-cast ballast 

around the base of the tank, 

may be used. Ensure that 1” 

to 2” of concrete is placed 

beneath the tank base if pre-

cast ballast is used. If the 

concrete is pre-cast, lifting 

hooks must be anchored in the 

ballast to support subsequent 

handling of the tank (see Lifting 

Instructions). The lifting hooks 

used must be adequate to 

support the combined weight of 

the tank and concrete ballast 

and shall be sized and installed 

in accordance with the site 

engineer’s recommendation.  

Place the ballasted tank on 

the gravel bedding in the 

excavated hole using the 

lifting hooks. Do not lift by 

any of the tank surfaces if 

pre-cast ballast is utilized

 3. INLET LOCATIONS:

 

A 4” DWV (standard)  inlet 

grommet was provided with 

the station for sealing the 

inlet pipe at the tank wall. If 

the inlet grommet penetration 

was not factory installed, the 

location of the tank inlet must 

be determined to support final 

positioning of the tank prior to 

ballast installation (see Section 

2). The inlet pipe location 

corresponds with the actual 

or projected point where the 

building sewer line intersects 

the tank wall. The grade of 

the inlet pipe and required 

burial depth (per national 

and local code requirements) 

must be accounted for when 

determining the inlet location. 

The supply cable path 

should be considered when 

selecting the inlet location (see 

Section 8). A 5” diameter field 

penetration of the tank wall is 

required to support installation 

of the (standard) inlet grommet. 

This penetration must not 

remove or interfere with any 

of the structural ribbing on the 

polyethylene tank. The inlet 

grommet may be installed in 

any of the allowable locations 

shown in Figure 7. The inlet 

penetration 

must

 be centered 

in the location selected to 

prevent interference with 

the tank ribbing. Typical inlet 

installation will be on one of 

the four, 10.5” diameter raised 

pads on the tank body. The 

pads have been marked with 

a series of locating lines to 

support centering of the 5” 

(standard)  drilled penetration. 

Any inlet installed in the 

depressed panels between the 

horizontal and vertical ribbing 

must be centered within the 

panel to provide adequate 

clearance for the 6” diameter 

flange on the standard 4” inlet 

grommet (Figure 7). Once the 

location of the inlet penetration 

is selected, mark the inlet 

center location on the tank 

and position the tank. Using 

a 5” diameter hole saw for 

a standard 4” grommet, drill 

through the tank wall at the 

marked location. Remove any 

chips or burrs from the drilled 

hole. Install the provided inlet 

grommet into the drilled hole. 

The grommet is self-sealing 

TYPICAL IN-GROUND SECTION VIEW

Figure 3

Содержание Extreme Series

Страница 1: ...1 WH48 WR48 Series Simplex Duplex Triplex Quadplex Typical Installation Instructions Warranty Information 486 Gal Capacity Grinder Pump Station ...

Страница 2: ...4 DWV 4 5 OD Supplied by others 9a STUB OUT 4 X 5 long watertight stub out to be installed at time of burial unless the gravity serviceline is connected during installation Supplied by others 10 DISCHARGE FTG 1 1 4 Female NPT stainless steel 11 DISCHARGE LINE 1 1 4 Nominal pipe size Supplied by others 12 CONCRETE ANCHOR See Ballast Calculations for specific weight for your station height Supplied ...

Страница 3: ...3 FAILURE TO COMPLY WITH INSTALLATION INSTRUCTIONS WILL VOID WARRANTY Figure 1 ...

Страница 4: ... standard grommet for connecting the 4 DWV 4 50 outside dia incoming sewer drain Other inlet types and sizes are optional CAUTION 4 DR 35 pipe has a smaller diameter and won t create a watertight joint with the standard 4 SCH 40 inlet grommet Confirm that you have the correct inlet before continuing Do not drop roll or lay tank on its side This will damage the unit and void the warranty Excavate a...

Страница 5: ...ximately 1 to 2 of concrete onto the gravel bed and place the tank into the excavation Ensure the tank is properly positioned in the excavation to support inlet pipe Section 3 and discharge pipe Section 5 connections before pouring the concrete ballast The unit should be leveled and filled with water about 24 deep to prevent shifting while the remaining ballast is being poured The concrete should ...

Страница 6: ...l depth per national and local code requirements must be accounted for when determining the inlet location The supply cable path should be considered when selecting the inlet location see Section 8 A 5 diameter field penetration of the tank wall is required to support installation of the standard inlet grommet This penetration must not remove or interfere with any of the structural ribbing on the ...

Страница 7: ...rge piping connection Note Models 481 and 482 will have single discharge pipe connection models 483 and 484 will have two discharge pipe connections 180 degrees apart standard 6 BACKFILL REQUIREMENTS Proper backfill is essential to the long term reliability of any underground structure Several methods of backfill are available to produce favorable results with different native soil conditions The ...

Страница 8: ...40 amp breaker is required before a 120V duplex alarm panel 9 ELECTRICAL CONNECTION Pump to Panel Fig 4 The grinder pump station is provided with a cable for connection between the station and the alarm panel supply cable for each grinder pump The supply cable a six conductor tray cable meets NEC requirements for direct burial as long as a minimum of 24 burial depth is maintained Those portions of...

Страница 9: ...anel will also contain one simplex or two duplex circuit breakers to control grinder pump power The pump circuit breaker s are labeled PUMP in the alarm panel For each grinder pump in the station perform the following procedure to verify proper installation and operation a Make sure that the slide face discharge valve s is fully open for each pump connection This valve s must not be closed when th...

Страница 10: ...10 ...

Страница 11: ...act as guides while aligning the bolt pattern of the two flanges 5 Support the upper accessway section a few inches over the tank Align the aluminum cover locking hasp on the fiberglass accessway section with the stainless steel discharge connection on the polyethylene tank Figure 6b Once aligned lower the upper section onto the mating flange using the three bolts to guide it to the proper positio...

Страница 12: ...12 Figure 7 ALLOWABLE INLET LOCATIONS INLET INSTALLATION ...

Страница 13: ...13 Figure 8 Figure 9 Figure 10 Figure 11 ...

Страница 14: ...tation or move it on its side 2 No Ballast to be poured in place If the concrete anchor is to be poured while the station is in place lift the unit using 2 nylon straps wrapped under the tank flange to make a sling as shown below Keep station oriented vertically to avoid any damage 3 Precast Ballast Never lift a station that has a ballast attached by any means except the rebar The weight of the co...

Страница 15: ... soil Section I Used To Determine The Volume Of Concrete Note 4 0 ft assumed inside diameter of concrete ballast ring around tank s bottom flange Volume Height Area 83 ft π 5 6 ft 2 4 0 ft 2 4 83 ft 12 06 ft2 10 1 ft3 Section II Used To Determine The Volume Of Saturated Soil Note 4 3 ft assumed inside diameter of soil column around tank s maximum diameter Volume Height Area 7 6 ft 83 ft π 5 6 ft 2...

Страница 16: ...application Station Height in Station Volume cu ft Fnet Buoyant lbs Tank Weight lbs Fballast lbs Volume Concrete cu ft Weight Concrete in Air cu ft Min Diameter of Concrete Anchor in Min Thickness of Concrete Anchor in 75 71 6 4088 380 4706 10 1 1515 68 10 92 85 1 4873 440 5623 10 1 1515 68 10 98 90 1 5175 445 5980 10 1 1515 68 10 104 95 0 5478 450 6330 10 1 1515 68 10 110 99 9 5780 455 6687 10 1 ...

Страница 17: ...17 ...

Страница 18: ...18 Environment One Corporation 2773 Balltown Road Niskayuna New York 12309 1090 Voice 01 518 346 6161 Fax 518 346 6188 www eone com NA0251P01 Rev E 10 18 A Precision Castparts Company ...

Страница 19: ...l Sanitary napkins or tampons Cigarette butts Caution Kitchen garbage disposals do not keep grease oil out of the plumbing system In addition you must never introduce into any sewer Explosives Strong chemicals Lubricating oil and or grease Flammable material Gasoline Items introduced into the sewer system from your home can potentially impact the water environment Proper disposal of household wast...

Страница 20: ... provided the product is properly installed serviced and operated under normal conditions and according to manufacturer s instructions Repair or parts replacement required as a result of such defect will be made free of charge during this period upon return of the defective parts or equipment to the manufacturer or its nearest authorized service center Limited Warranty For E One Extreme D Series W...

Отзывы: