3    Installation and Configuration

 

3.1    Preparations for installation

 

Safety Requirement

 

The product can only be installed by personnel who have been trained in the power-supply system 
and have sufficient knowledge of the electrical power system. 

 

The safety regulations and local safety regulations listed below should always be followed during 
the installation.

 

 

 

All circuits connected to this power system with an external voltage of less than 48V 
must meet the SELV requirements defined in the IEC60950 standard. 

 

If  operating  within  the power  system  cabinet,  make  sure  the  power  system  is  not 
charged. Battery devices should also be switched off. 

 

Distribution cable wiring should be reasonable and has the protective measures to 
avoid touching these cables while operating power equipment. 

 

when installing the battery system, must wear the protective items below: 

The isolation gloves                    Safety goggles

 

                      Safety shoes         

 

3.1.1    Environmental requirements

 

Working temperature: -20

 o

C ~ +55

 o

C

 

 

Charging temperature range is 

0

o

C~+55 

o

C, 

 

 

Discharging temperature range is -20 

o

C ~+55 

o

C

 

Storage temperature: -10

 o

C ~ +35

 o

C

 

Relative humidity: 5% ~ 85%RH

 

Elevation: no more than 4000m 

 

Operating environment: Indoor or outdoor installation should avoid the sunlight and wind, 
no conductive dust and corrosive gas.

 

 

The following conditions shall be met:

 

 

Installation location should be away from the sea to avoid corrosion from brine or 
high humidity environment.

 

 

The ground for product arrangement shall be flat and level.

 

 

Ensure there is no flammable explosive materials near to the installation places.

 

 

The optimal ambient temperature is 15

o

C ~ 30 

o

C

 

 

Keep away from dust and messy zones

 

Содержание PowerDepot H5

Страница 1: ...V1 1 PowerDepot H5 User Manual ...

Страница 2: ...llation 7 3 1 1 Environmental requirements 7 3 1 2 Tools and data 8 3 1 3 Technical preparation 8 3 1 4 Unpacking inspection 8 3 1 5 Engineering coordination 10 3 2 Equipment installation 10 3 2 1 Floor installation 11 3 2 2 Mounted on the wall 12 3 2 3 Electrical installation 14 3 2 4 Battery module DIP switch definition and description 18 3 2 5 Battery parameter settings on the inverter 24 3 2 6...

Страница 3: ... requirements of environmental protection and personal safety The storage use and disposal of the products shall be carried out in accordance with the product manual relevant contract or relevant laws and regulations Customer can check the related information on the website of Daqin New Energy Tech Taizhou Co Ltd when the product or technology is updated Web URL http www dyness tech com cn Please ...

Страница 4: ...ce outer case bulging In order to ensure safety and normal use of the product the equipment should be grounded properly before use To assure the product normal operation please make sure parameters among the relevant device are compatible and matched Please do not mixed use batteries from different manufacturers different types and models as well as old and new together Ambient and storage method ...

Страница 5: ...n maintenance Safety Statement Only qualified and trained professionals are qualified to install operate maintain the device Please comply with local safety regulations and operational rules during installation operation and maintenance or it could cause unexpected injury or device damage The safety declaration mentioned in the manual are only supplement context for your local safety regulations T...

Страница 6: ...y storage product s anode materials are lithium iron phosphate battery cells are managed effectively by BMS with better performance The systems features as below Comply with European ROHS Certified SGS employ non toxic non pollution environment friendly battery Anode materials are lithium iron phosphate LiFePO4 high safety performance longer life span Equipped with BMS battery management system mo...

Страница 7: ... Be careful with your actions and be aware of the dangers Read the user manual before using The scrapped battery cannot be put into the garbage can and must be professionally recycled After the battery life is terminated the battery can continue to be used after it recycled by the professional recycling organization and do not discard it at will This battery product meets European directive requir...

Страница 8: ...ance Parameter Table 2 2 PowerDepot H5 performance parameter Item PowerDepot H5 2 5 PowerDepot H5 5 Nominal Voltage V 48V 48V Work Voltage Range V 42 54 42 54 Nominal Capacity Ah 50Ah 100Ah Nominal Energy kWh 2 4 4 8 Nominal Power kW 0 7 1 5 Max Power kW 2 4 4 8 1S Peak Power kW 2 64 5 28 1S Peak Current A 55 110 Charging Current A 25 50 Discharge Current A 25 50 2 3 Interface Definition This sect...

Страница 9: ...on socket is connected to the COM OUT interface of the previous PowerDepot H5 through communication cable Factory default CAN communication mode 3 Negative socket The battery DC output negative pole which is connected to the negative pole of the inverter through the cable 4 COM OUT When the system is used independently This CAN RS485 socket is a reservation interface When the system is used in par...

Страница 10: ...current protection Temperature abnormality etc Other case Alarm Yellow green and red flash alternately All module address assignments in the system are incomplete The master PowerDepot H5 LED1 yellow flash Communication failure between batteries 2 4 Battery Management System BMS 2 4 1 Voltage Protection Low Voltage Protection in Discharging When any module cell voltage is lower than the rated prot...

Страница 11: ... protection be activated device stops charging The protection is released when it back to rated range of working temperature Low Over temperature protection in discharging When battery s temperature is beyond range of 20oC 55oC during discharging temperature protection be activated device stops supplying power to the outside The protection is released when it back to rated range of working tempera...

Страница 12: ...tective measures to avoid touching these cables while operating power equipment when installing the battery system must wear the protective items below The isolation gloves Safety goggles Safety shoes 3 1 1 Environmental requirements Working temperature 20 o C 55 o C Charging temperature range is 0o C 55 o C Discharging temperature range is 20 oC 55 oC Storage temperature 10 o C 35 o C Relative hu...

Страница 13: ... supply equipment The DC standby interface and the maximum discharge current shall be higher than the maximum charging current of the products used in table 2 2 If DC interface maximum discharge capacity of the user s equipment is less than the maximum charging current of products using in table 2 2 the user s interface should have the power equipment of DC current limiting function to ensuring th...

Страница 14: ...guration table and packing list ensure objects are complete and intact If the internal packaging is damaged it must be inspected and recorded in detail Packing list is as follows Battery 1 Battery bottom bracket 1 Support bracket 2 M6 bolt 8 Fixing battery box with battery bracket Power cable 2 connect battery with inverter Standard Communication cable 1 User manual 1 Positioning cardboard 2 Expan...

Страница 15: ...e and bearing capacity Make sure that the battery has enough space to install and that the battery rack and bracket have enough load capacity Wiring Make sure the power cable and ground wire are reasonable Not easy to short circuit water and corrosion 3 2 Equipment installation The wall for battery installation shall be solid brick or cement wall with strong bearing capacity and wall thickness no ...

Страница 16: ...e connection 3 2 1 Floor installation When the battery system is placed directly on the ground a fixed support must be used to fix the top of the battery box on the wall 1 Use the positioning cardboard provided in accessory package and mark the screw hole positions on the wall as shown four holes in the picture on the left 2 The bottom of the board must be in horizontal touch with the ground while...

Страница 17: ...ttom bracket 1 Expansion screw 4 4 Fixing the shell of the M6 expansion bolt into the hole on the wall 5 Use the M6 bolt to fix the Support bracket on the wall and control the torque force at 6NM 6 Carry the battery box to the installation site and place it at 15mm away from the wall surface Connect the support bracket and the battery box with M6 bolts ...

Страница 18: ...und while marking the holes 3 The bottom of the cardboard is about 300mm to the ground 4 According to the marked position use an electric drill to drill 8 holes with a diameter of 10mm on the wall for installing M6 expansion bolts The depth of the holes should be greater than 70mm 5 Fixing the shell of the M6 expansion bolt into the hole on the wall and fix the Support bracket and Battery bottom b...

Страница 19: ... testing of power line connection the positive and negative poles of the battery shall be connected respectively to the positive and negative poles of another device inverter Connect the battery box to the ground cable Customer needs to prepare a M6 OT terminals and ground cables Connect the battery shell as shown below The sectional area of the grounding cable shall be at least 6mm and the bolt l...

Страница 20: ... the battery ID and give device opening operation authorization Except changing the DIP switch mode no other operations can be done The connection between inverter and battery should apply the power cable and communication cable which has been offered in your accessory package the communication cable is standardized type and The applicable inverter module has been indicated on the cable Label Plea...

Страница 21: ...oot position Color Definition PIN1 Orange white 485A PIN2 Orange XGND PIN3 Green white 485B PIN4 Blue CANH PIN5 Blue white CANL PIN6 Green Reserved PIN7 Brown white XIN PIN8 Brown Reserved POWERBOX INVERTER Battery Battery CAN IN Battery CAN CAN OUT PowerDepot H5 ...

Страница 22: ...n parallel as an example the system needs to use Power cable 3pair Battery Inverter communication cable 1PCS Battery Battery communication cable 2PCS Distribution box 1PCS The over current capacity of the distribution box should be much higher than the maximum nominal current value when the load is running PINOUT of system parallel communication cable PINOUT of Battery Battery communication cable ...

Страница 23: ... Baud rate selection OFF OFF slave OFF CAN 500K 485 9600 ON host ON CAN 250K 485 115200 DIP switch description For PowerDepot H5 series system the No 1 module near the front panel side is the host another one is slave INVERTER Battery Battery Battery CAN POWERBOX No 1 POWERBOX No 2 POWERBOX No 3 Power distribution box CAN IN CAN OUT CAN IN CAN OUT CAN IN CAN OUT PowerDepot H5 Master PowerDepot H5 ...

Страница 24: ...mmarizes the information of the entire battery system and communicates with the inverter through CAN or 485 The communcaiton mode is shown as blew Slave module DIP Switch mode 1 ADD 0010 DIP Switch mode 2 ADD 0100 DIP Switch mode 5 ADD 0000 DIP Switch mode 3 ADD 0110 No 1 Module Host module Front panel DIP Switch mode 4 ADD 1001 DIP Switch mode 6 ADD 0001 ...

Страница 25: ...pert king Axpert VMIII Growatt SPH SPA CAN comm GMDE Saj 485 comm change the host module DIP switch to 0100 2 to ON before connecting 4 If the battery communicates with the Growatt SPF HVM P ES WPV by RS485 communication change the host module DIP switch to 0110 2 3 to ON before connecting 5 If the battery communicates with the ICC by 485 communication change the host module DIP switch to 1001 1 4...

Страница 26: ...t The list of compatibility between Dyness ESS and Inverters Caution 1 The DIP switch Mode 4 and Mode 6 is only for ICC a special commnunication device for some no communication inverter it s a specia firmware in PowerDepot H5 different from general firmware so if customers want to use that please contact dyness to confirm 2 Generally factory default DIP switch status of the host module in PowerDe...

Страница 27: ... the cover with four screws which were removed in step a Note Confirm the positive and negative interface of battery output terminal and inverter input terminal The red power cable is for connection of the battery s positive to inveter s positive and the black power cable is for the connection of battery s negative to inveter s negative Before connection it is necessary to confirm the charge and d...

Страница 28: ...y module number of modules If the equation holds after calculation it means communication between PowerDepot H5 and PowerDepot H5 is normal 2 If the PowerDepot H5 light board shows three different colors flash alternately it means the communication between PowerDepot H5 is fault Table 3 3 Battery Inverter power matching table Power of Hybrid Inverter Off grid Inverter PowerDepot H5 Type System Ene...

Страница 29: ...A Max Discharge Current PowerDepot H5 2 5 25A PowerDepot H5 5 0 50A Capacity PowerDepot H5 2 5 50Ah PowerDepot H5 5 0 100Ah 3 2 6 Register on the website after installation After the battery system installation is completed and the running is normal you need to log in to the DYNESS official website to register the product installation and use information to make the product warranty effective Plea...

Страница 30: ...the battery status indicator lights shows abnormally please refer to the 4 2 Alarm description and processing If the failure cannot be eliminated please contact the retailer timely 3 Use a voltmeter to measure whether the voltage across the BAT BAT terminals of the inverter is higher than 42V and check whether the voltage polarity is consistent with the input polarity of the inverter If the voltag...

Страница 31: ...ction and temperature protection in the system please refer to Table 4 1 Table 4 1 Main alarm and Protection Statue Alarm category Alarm indication Processing Charge state Over current RED light flashing Buzzer start Reduce the charging current below the rated value High temp protection RED light flashing Stop charging and find out the cause of the trouble Discharge state Over current RED light fl...

Страница 32: ...of the DC circuit breaker on the side of cabinet 3 No DC output and red light flashing buzzer beeping Battery voltage is too low Charging the battery system 4 The battery cannot be fully charged Charge voltage is low Adjust charging voltage within 53 5V 54V range 5 The power cable sparks when system power on and ALM indicated Red light on Power connection short circuit Turn off the battery check t...

Страница 33: ... 28 Daqin New Energy Tech Taizhou Co Ltd Address Building 13 Kunshan Jiangyan Industrial Park Chenzhuang West Road Jiangyan District Taizhou City Jiangsu Province China 225500 Email sales dyness net Website http www dyness tech com cn ...

Отзывы: