10 |
WID EC U RE
®
C ON VEYO R U SER GU ID E
D YMAX. C O M
Conveyor Setup
Installation and Interconnection
Your
WIDECURE
UV light-curing conveyor system requires minimal assembly once removed from the packing skid or crate.
1.
A certified electrician should provide 460 VAC, 3Ø, 60Hz, 30A supply. The junction box on the right side of the system contains
four #8 AWG MTW wires. The electrical supply connection must be hard-wired by a professional, licensed electrician. (Figure 4)
NOTE: The machine will ship with a blank cover-plate installed. The end user shall decide whether the machine is hard-wired
with a flexible cable, or routed with metallic conduit. Suggested conduit entrances are from the top, bottom, or rear of the
machine.
2.
Verify that the UV shielding is installed on the outlet side of the conveyor. The shielding is designed to minimize UV exposure to
the operator.
Figure 4. Power Supply Wiring
Figure 5. UV Shielding
3.
The irradiator is mounted on a linear stage that allows the height of the curing lamp to be adjusted from the conveyor belt. Use
the control functions on the HMI to move the UV irradiator up or down as needed to allow for parts clearance and/or optimized
cure height.
NOTE: The UV light should be turned off before you look into the curing chamber to make an adjustment on the irradiator height
or for any other purpose.