DOOSAN INFRACORE 3/36
3
1. Periodic Maintenance List
项目
Object of Maintenance
INTERAVAL
Lifting Unit
1
Chain
3 month
2
Proximity Switch
1 month
3
Guide Rail and Block
3 month
4
Lifting Mechanism
3 month
5
Limit Switch
3 month
6
Remove chips and coolant
1 Week
Traveling
Unit
1
Travelling Mechanism
3 month
2
Limit Switch
3 month
3
Traveling Rail
3 month
4
Rail Guide
3 month
5
Cable Carries
1 month
Forking Unit
1
Forking Mechanism
1 month
2
Chain
1 month
3
Guide Bearing
3 month
4
Limit Switch
3 month
5
Remove chips and coolant
1 week
SET UP
STATION
1
Air service unit
1 month
2
Proximity Switch
3 month
3
Remove chips and coolant
1 week
Rack
1
Remove chips and coolant
1 week
Base Fram
2
Lubrication Of Rack gear
1 month
3
Remove chips and coolant
1 week
注意
1. 每 1 个月检查的周期是 1 个月
2. 每 3 个月检查的周期是 3 个月
3.
同时进行每 1 个月、每 3 个月及每 1 年检查时应检查包括全项目