Installation, Operation and Maintenance manual
9
PowerCore
®
Dust Collectors - Series CPV
Angle not
to exceed 30°
from vertical
Do not lift
with this orientation
30°
Figure 2: Four-point lifting arrangement (CPV-6 and CPV-6F illustrated)
Mounting over aperture
1. Check that the aperture and fixing holes are correct in size and position to suit
the mounting-flanges of the PowerCore dust collector (details of aperture and
mounting flange fixing positions are provided in Publication 3020).
2. Apply a continuous 5 mm bead of sealing compound all round aperture, along
each side of the fixing holes, as shown.
3. Following the general guidance to lifting, lift and position the collector until the
mounting-flange is seated in position over the aperture. Match up fixing-holes,
install bolts, washers and nuts and tighten down all round to form an airtight seal.
Fixing bolts etc. are not supplied by Donaldson.
Compressed air requirements
PowerCore dust collectors require an independent supply of clean, dry, oil-
free compressed air. Details of atmospheric pressure and quantity are given in
Table 4 (refer to ‘Specification’ section). A design label is also attached to each
manifold. Where an existing factory mains system is to be used it may be necessary
to install an additional moisture separator in the supply line to the collector. If a
compressor is being installed to supply the collector, then the following conditions
should be observed as far as possible: