Inlet Hopper with Flex-Duct
1. Lift the collector high enough to assemble.
2.
Apply sealant around the flex-duct collar toward the outside of the bolt pattern.
3.
Align the flex duct collar with the bottom flange of the hopper. Fasten using bolts, washers, and hex nuts supplied.
4.
Apply sealant around the hopper’s top flange toward the outside of the bolt pattern.
5.
Align the top flange of the hopper with the bolt pattern on
the bottom of the collector and secure using 6mm bolts and
washers supplied.
Note: Install a 6mm bolt into every rivnut.
6.
Fasten one end of the flexible duct to the collar using a six
inch hose clamp.
7. Position the inlet collar on the machine center and trace the
inlet opening and bolt pattern. Remove inlet collar, cut inlet
hole, and drill bolt holes using a 3/16-in diameter drill bit.
8.
Apply a 1/4-in bead of sealant to the machine center, toward
the outside edge of the bolt pattern.
9. Align collar and fasten to machine center using 1/8-in
customer-supplied bolts, washers, and hex nuts.
10.
Trim the flexible duct to the required length and secure with
remaining hose clamp.
Do not allow flexible duct to create a
P-Trap. See Flex-Duct Positioning.
hopper
see sealant detail
flex-duct collar
hose clamp
flex-duct
hose clamp
inlet collar
see sealant detail
sealant
bolt hole
Sealant Detail
Inlet Hopper with Flex-Duct
Inlet Hopper with Vibration Isolators
1. Carefully lift collector and turn over so the bottom inlet is
facing up.
2.
Remove plugs or existing hardware from the five holes on
the collector’s left side (exhaust side).
3.
Apply sealant to the leg’s top flange and secure to collector
using the hardware removed in Step 2.
4.
Apply sealant to the inlet collar toward the outside edge of the bolt pattern. Fasten inlet collar to the hopper’s bottom flange
using the bolts, washers, and hex nuts supplied.
5.
Apply sealant around the hopper’s top flange toward the outside of the bolt pattern.
6.
Align the top flange of the hopper with the bolt pattern on the bottom of the collector and secure using 6mm bolts and washers
supplied.
7. Attach remaining leg to the right side of the collector following the same procedure.
8.
Turn collector upright, lift into position over the machine center and lower slowly. Do not remove crane.
Donaldson Company, Inc.