12.1
Feed auger filling
During the commissioning of the boiler, before calibrating the feed auger or if the hopper runs out of
fuel,
it is compulsory
to fill of fuel the feed auger. By means of this parameter the feed auger will be
filled of fuel, process required for a correct boiler functioning.
When
“Feed auger filling”
parameter is displayed (
) on
"Calibration
Menu"
, press
to access. SET symbol blinks and pressing
again
it will be activated filling procedure. The feed auger will be activated
and a count up to 15 minutes (maximum) will be displayed. During the
process by pressing
the feed auger could be stopped at any time
and by pressing RESET the filling procedure could be finished and
return to
"Calibration Menu"
at any time.
To ensure a complete filling of boiler feed auger it is recommended to make a complete 15 minute
procedure of filling, at least once. Follow the steps shown in the following pictures for a correct filling
of the feed auger:
IMPORTANT: It is compulsory to fill the feed auger during the commissioning or when
the hopper runs out of fuel.