Planning the installation site
Requirements for the wall, floor and mounting
system
► The inverter is heavy. The wall, floor and mounting
system must be able to bear the weight of the invert-
er.
►
Always use the mounting plate supplied with the
inverter for wall mounting.
►
Use mounting materials (dowels, screws, etc.) suit-
able for the wall or the mounting system, as well as
the weight of the inverter.
►
Mount the inverter on a vibration-free wall to avoid
faults.
►
When using the inverter in residential areas or in
buildings with animals, possible noise emissions can
be disturbing. Therefore, choose the installation loca-
tion carefully.
► Mount the inverter on a fireproof wall.
Special notes on ground mounting
In principle, the inverter can be mounted directly onto the
ground or directly onto the roof in the case of roof systems.
If there is a risk of flooding (for example in
heavy rain) or snow drifts, you should install
the inverter in an elevated position.
Installation position
►
Mount the inverter vertically.
Installation site
Outdoor installations
UV
The inverter has a protection degree of IP66 and can be
installed indoors and outdoors. Despite this, the inverter
should be protected by a roof against direct sunlight, UV
radiation, rain and snow.
For example, the power of the inverter will be reduced if it
heated excessively by sunlight. This is normal operating
behavior for the inverter and is necessary to protect the
internal electronics.