l
Redundant power supply units are required.
l
Non-EMC qualified peripheral cards and/or peripheral cards greater than 25 W are
not supported.
l
Mid drive tray is not supported.
l
Rear storage devices or drives are not supported.
l
GPU is not supported.
Thermal restrictions
Following table lists the configuration required for efficient cooling.
Following table describes the configuration required for efficient cooling.
Table 29 Thermal restrictions configuration
Supported
VxRail
Config
Number
of proc
Heatsink
Processor/DIMM
blank
DIMM
blanks
Type of air
shroud
Fan
VxRail P
Series
appliance
1
One 1U standard heat sink
for CPU ≤ 125 W
Required
Not
required
Standard
Four standard
fans and one
blank to cover
two fan slots
One 2U standard heat sink
for CPU > 125 W
VxRail P
Series
appliance
2
Two 1U standard heat sink
for CPU ≤ 125 W
Not required
Not
required
Standard
Six standard
fans
Two 2U standard heat sink
for CPU > 125 W
VxRail S
Series
appliance
1
One 1U high performance
heat sink
Required
Required
Not required
Six high
performance
fans
VxRail S
Series
appliance
2
Two 1U high performance
heat sink
Not required
Required
Not required
Six high
performance
fans
VxRail V
Series
appliance
2
Two 1U high performance
heat sink
Not required
Not
required
GPU air shroud Six high
performance
fans
Particulate and gaseous contamination specifications
The following table defines the limitations that help avoid any equipment damage or
failure from particulates and gaseous contamination. If the levels of particulates or
gaseous pollution exceed the specified limitations and result in equipment damage or
failure, you may need to rectify the environmental conditions. Remediation of
environmental conditions is the responsibility of the customer.
Air filtration specification: Data center air filtration as defined by ISO Class 8 per ISO
14644-1 should have a 95% upper confidence limit. Note: This condition applies only to
data center environments. Air filtration requirements do not apply to IT equipment
designed to be used outside a data center, in environments such as an office or
factory floor. Note: Air entering the data center must have MERV11 or MERV13
filtration. Conductive dust specification: Air must be free of conductive dust, zinc
whiskers, or other conductive particles. Note: This condition applies to data center
and non-data center environments. Corrosive dust specification: Air must be free of
Technical specifications
Particulate and gaseous contamination specifications
35