![DASS Tech Soleaf DASS 100i Скачать руководство пользователя страница 40](http://html1.mh-extra.com/html/dass-tech/soleaf-dass-100i/soleaf-dass-100i_operation-and-installation-manual_3597067040.webp)
39
5. Operation
5.1 Checklist prior to Operation
①
Once the connection is complete between PV cable and AC cable, the inverter is ready for
startup.
②
Turn the DC switch in the lower part of the inverter to the ON direction then, Turn the DC
switch to the ON direction. The factory default setup of the product is OFF.
③
Upon the AC turned ON, the inverter counts 300 sec for automatic startup. The count time can
be checked at the right upper end of the external LCD.
④
Once 300 sec is passed, the inverter is started up automatically and runs below the operation
voltage, it is stopped automatically.
5.2 Appearance of the Display Window and Functions