Procedure
1.
Check that the delivery agrees to the order, see
2.
Before starting the commissioning, read carefully the safety instructions in
3.
Before the mechanical installation, check the minimum clearances around the unit (
4.
,
6.3 EMC-compliant Installation
.
5.
Obey the installation instructions, see
6.
Find information on the control connections in
7.3.2 Control Terminals on OPTA1
7.
If the start-up wizard is active, select the language of the control panel and the application. Accept the selections with the Enter
button. If the start-up wizard is not active, obey the instructions a and b.
A
Select the language of the control panel from the Menu M6, page 6.1. For instructions, see
.
B
Select the application from the Menu M6, page 6.2. For instructions, see
8.7.4 Changing the Application
8.
All parameters have factory default values. To make sure that the AC drive operates correctly, make sure that these group G2.1
parameters have the same data as the nameplate. For more information on the parameters in the list, see the VACON
®
All in One
Application Manual.
•
Nominal voltage of the motor
•
Nominal frequency of the motor
•
Nominal speed of the motor
•
Nominal current of the motor
•
Motor cos phi
9.
Obey the commissioning instructions, see
9.2 Commissioning the Inverter
.
The VACON
®
NX Inverter is ready for operation.
Introduction
Operating Guide | VACON® NX Inverters FI4-FI8
AQ299433367205en-000101 / DPD00908
10 | Danfoss A/S © 2019.07
Содержание VACON NX FI6
Страница 1: ...Operating Guide VACON NX Inverters FI4 FI8...
Страница 2: ......
Страница 164: ...Operating Guide VACON NX Inverters FI4 FI8 AQ299433367205en 000101 DPD00908 164 Danfoss A S 2019 07...
Страница 165: ...Operating Guide VACON NX Inverters FI4 FI8 AQ299433367205en 000101 DPD00908 165 Danfoss A S 2019 07...