Shrink tube
8. Insert the cable through the corresponding hole in the connection box and connect the cable lug to
the connection point. Use spring washer between the cable lug and the connection screw or nut.
Example of the connection is shown in Figure below. Do not tighten the connection at this point to
ensure fitting of the cable gland.
Make sure that there is at least 10 mm air gap between the cable lug and other metallic
structures including the braid of the cable. If the air gap is smaller, use extra insulation
shrink tube to cover the lug.
Cable lug connection to the connection box (example only, the connection box may look different)
9. Screw the cable gland to the connection box as shown in the Figure above. Tighten the cable gland
from the body of the gland. See Chapter
Tighten from the body of the cable gland with the correct torque. Then tighten the cap of
the cable gland manually, but so that the insulation does not come out of the joint.
10. Tighten the cable lug. Use tightening torque of 15 Nm.