16.
As during assembly of the greenhouse the bolts have been tightened loosely in order to be able to easily
move profiles, if needed, the next step is to adjust the assembled frame of the greenhouse with the level, to
check the diagonal once again, to tighten bolts fully, and only after that to fill up the holes (Fig. 16).
Fig. 16
Be careful not to mix sides of polycarbonate! Fasten it with a set side to the outside, where there is a
UV rays protection layer. UV rays protection layer is coated by a film with inscriptions; another side
(being installed to the inside) is coated by a transparent film. It is recommended to cut sheets with an
electric circular saw, a hand saw with small teeth, a sharp knife, if necessary. Before installation it is
necessary to remove films! SAFETY GLOVES ARE NECESSARY TO WEAR WHEN CUTTING
SHEETS
!
17.
Upon tightening the frame part of the greenhouse installation of polycarbonate is to be started. Start
fixing polycarbonate sheets from the rear part of the greenhouse. Apply the part of back wall polycarbonate
sheet below window (1020x1230 mm) to the frame on the back side of the greenhouse and tighten it with
M5-40 bolts (29), M5 nuts (30), and gaskets (31). Through connection plates (21) polycarbonate is tightened
with M5-20 bolts (27), M5 nuts (30), and gaskets (31). Then cut polycarbonate near the frame profile with a
sharp knife or a jigsaw, if necessary. Upper polycarbonate channels in the part below window depending on
configuration are sealed by U-profile or breathing strip (34) (Fig. 17.1
–
17.4).
Fig. 17.1