9. FIRST START-UP 

 

Before starting up the electropump check that in the tank system there is no residue or other 
material that could harm the correct operation of the system. 

 
In this phase you can leave the interception valve in the inlet pipe closed and fill the lifting station with clean 
water. Open the interception valve in the delivery pipe and check that the pipes are tightened and perfectly 
sealed and that the electropump is working correctly. Check also that the electropump is primed. Open the 
interception valve in the inlet pipe and check that the station is working correctly. 

 

The flow of liquid coming from the various utilities must not prevent the correct operation of the 
floats present in the container. 

In the case of a three-phase electropump, check that the impeller is turning in the correct direction. Check 
also the electropump manual. Check that the levels of float intervention are correct, and if necessary adjust 
them to suit the actual needs of the system. When there are two electropumps, the floats must be adjusted 
so that the second pump starts after the first and only if the first is not able to send to the sewer duct as 
much liquid as arrives from the various utilities. Check that the electropump cannot become unprimed during 
operation. Check that the number of starts per hour is compatible with the characteristics of the system 
components. Check that the system is working correctly and put it into service. Close the cover or covers of 
the station, screwing them into place. If necessary, fix the cover in its seat in such a way as to prevent 
unauthorised opening of the cover (see chapter 5.7). 
 

9.1  Operating flow rate 

It must be guaranteed that the speed of the liquid in the delivery pipe is at least 0.7 m/s and lower than 2.3 
m/s. 
 

9.2 Operation 

When the liquid in the tank reaches the level corresponding to the closure of the float contact that commands 
the electropump, the pump starts and gradually empties the container. The electropump stops when the 
liquid reaches the minimum level corresponding to the opening of the float contact. When there are two 
electropumps, the floats must be adjusted so that the second pump starts after the first and only if the first is 
not able to send to the sewer duct as much liquid as arrives from the various utilities. There may be a float 
placed higher than the others in the pumping station, its function is to indicated the presence of an 
abnormally high level of the liquid in the tank. 
 

10. MAINTENANCE 

After starting up the plant, it is advisable to inspect and clean it, especially the no return valve, about every 
three months. This interval may be increased after the first inspections have given a favourable outcome. 
Clean the pump accurately, removing any foreign bodies stuck in the intake grille and check that the float 
moves freely. If necessary, remove the pump from the tank. 
It is recommended to clean the system at least once a year with running water, operating the pump 
repeatedly. 
 
 
 
 
 
 
 
 
 
 
 
 
 

Содержание FEKABOX 200

Страница 1: ...ONSANWEISUNG UND WARTUNG INSTRUCTIES VOOR INGEBRUIKNAME EN ONDERHOUD INSTRUCCIONES PARA LA INSTALACION Y EL MANTENIMIENTO N VOD K INSTALACI A DR B INSTRUKCJA MONTA U I KONSERWACJI KURMA VE BAKIM B LG...

Страница 2: ...onnecting the delivery pipe to the sewer network 43 5 6 Connecting the ventilation pipe 43 5 7 Closing the cover 43 5 8 Provision for emergency drainage 44 5 9 Non return valve 44 5 10 Interception ga...

Страница 3: ...pliance by a person responsable for their safety Children should be supervised to ensure that they do not play with the appliance 1 3 Check that the system has suffered no damage during transport or s...

Страница 4: ...he level of the sewer network In compliance with the accident prevention regulations in force the FEKABOX FEKAFOS cannot be used for conveying inflammable or explosive liquids such as petrol diesel fu...

Страница 5: ...4 1 Dimensions and weights The adhesive label on the package indicates the total weight of the system The dimensions below are given in millimetres Only for Fekabox 200 Fekafos 280 280 Double Fekafos...

Страница 6: ...se the surface on which it is laid must be perfectly horizontal and it must be ensured that the whole bottom of the tank is in contact with the surface For Fekabox 200 l Fekabox 280 and Fekabox 550 Do...

Страница 7: ...rked with the symbol Make a hole in the tank in the determined areas indicated by the symbols shown above To make the hole use a hollow cutter as shown in figure 5 indicative figure with the correct d...

Страница 8: ...gases cannot get into other places such as buildings rooms and similar Avoid horizontal stretches in the ventilation duct 5 7 Closing the cover Check that the gasket of the cover is lying in the botto...

Страница 9: ...public private sewer network This will avoid the reflux of liquid Place the valve at a distance of at least 1 metre from the lifting station to allow the flow of liquid moved by the pump to open the s...

Страница 10: ...therefore intended for only one automatic single phase pump with float 20Kg A Remove the tank cover B Extract the slide 3 from the coupling foot 5 C For FEKA 600 screw the special 2 F 1 1 4 M couplin...

Страница 11: ...ENGLISH 46 FEKABOX 200 l PREPARED FOR THE FOLLOWING PUMPS FEKABOX 200 FEKA 600 MA FEKA VS VX 550 MA FEKA VS VX 750 MA FEKA VS VX 1000 MA FEKA VS VX 1200 MA FEKA VS Fig 8A Fig 8B FEKA 600 Fig 8 FEKA VX...

Страница 12: ...the top screw from the flange on the delivery side 1 Assemble the anti rotation bracket 2 Replace the screw 1 Extract the slide from the coupling foot 5 and connect it to the delivery port of the pump...

Страница 13: ...R 1800 T GRINDER 1000 1200 1600 MNA TNA FEKA 2015 2 MNA TNA 2025 2 2030 2 TNA PREPARED FOR THE FOLLOWING PUMPS FEKAFOS 280 DOUBLE FEKA VS VX 550 MNA TNA FEKA VS VX 750 MNA TNA FEKA VS VX 1000 MNA TNA...

Страница 14: ...OS 550 DOUBLE FEKA VS VX 550 MNA TNA FEKA VS VX 750 MNA TNA FEKA VS VX 1000 MNA TNA FEKA VS VX 1200 MNA TNA FEKA GRINDER 1400 M FEKA GRINDER 1800 T GRINDER 1000 1200 1600 MNA TNA FEKA 2015 2 MNA TNA 2...

Страница 15: ...he Dab Assistance Service for the commissioning of the system For connecting the system it is recommended to use exclusively the panels ED E BOX indicated by the manufacturer supplied complete with de...

Страница 16: ...n the ring nut and connect the cable to the control panel as indicated in the respective manual taking care that the terminals on the panel correspond to the respective float cables TWO FLOATS THREE F...

Страница 17: ...to check the operation of the alarm system Make a test of the complete system with clean water checking that the alarm system intervenes only in the case of a pump malfunction or lack of power in the...

Страница 18: ...ck that the system is working correctly and put it into service Close the cover or covers of the station screwing them into place If necessary fix the cover in its seat in such a way as to prevent una...

Страница 19: ...e grille is blocked G The impeller is worn or blocked by foreign bodies A Remove the obstructions B Check that the pump slide is at its full limit only for 280 l tanks C Clean the valve D Open the val...

Отзывы: