5. TANK INSTALLATION 

The lifting stations of the Fekabox – Fekafos series have various inlet and outlet possibilities for the pipes. 
Depending on the type of installation and on the local standards in force it may be necessary to provide a 
siphon, a non-return valve on the pipe connecting to the public/private sewer network or to other ducts. 
Always refer to the local and/or national regulations, laws and standards in force. Anyway it is recommended 
to install check valves and interception valves upstream and downstream from the station. An example of 
installation is shown in chapter 4. 

 

All the ducts must be installed in such a way that they are not stressed. The ducts must not 
exert stress on the station. Check that the electropump is securely fixed to the pipes and that 
all the hydraulic connections are tightened and watertight. 

Where necessary provide suitable means for avoiding the transmission of vibrations and for protecting the 
pipes against the formation of ice.  
 

5.1  Placing the tank inside the building 

The tank may be laid on the floor, under the ground or housed in a masonry pit. Fig.2, Fig.3 

In any case the surface on which it is laid must be perfectly horizontal and it must be ensured that 
the whole bottom of the tank is in contact with the surface. 

 

For Fekabox 200 l, Fekabox 280 and Fekabox 550 Double  l the cover of the tank is trafficable 

(max. weight 100 Kg, see fig. 1). 

In indoor installations (garage, basement, technical room), the tank must be fixed to the 
ground using the slots provided to prevent rotations, as indicated in figure 4. 

 
 
 
 
 
 
 
 
 
 

 

Leave a free space of at least 60 cm around and above the station for installation and 
maintenance. 

 

5.2  Placing the tank outside the building 

If the tank would not buried, to prevent damage to itself and to the seals, you should not expose it to heat 
sources such as direct sunlight can be at certain times of the year. 

 

Do not position the lifting station directly on the ground. The site chosen must not have ground 
water and must not be subject to flooding. Suitable anchor the station so as to avoid rotation 
and floating. For this you can use the slots on the base of the tank. 
There must be a horizontal base suitable to bear the weight of the station during its operation. 
Depending on the characteristics of the terrain it may be necessary to create walls with bricks, 
prefabricated components or concrete. Fill the space between the ditch and the station with 
sand and compact it suitably. Protect the station suitably against frost.  

Fig. 4 

FIX THE TANK TO THE GROUND 
BEFORE USE 

Use screws TE M8 with respective 
fixture, use specific washers for soft 
materials ISO 7093

 

Содержание FEKABOX 200

Страница 1: ...ONSANWEISUNG UND WARTUNG INSTRUCTIES VOOR INGEBRUIKNAME EN ONDERHOUD INSTRUCCIONES PARA LA INSTALACION Y EL MANTENIMIENTO N VOD K INSTALACI A DR B INSTRUKCJA MONTA U I KONSERWACJI KURMA VE BAKIM B LG...

Страница 2: ...onnecting the delivery pipe to the sewer network 43 5 6 Connecting the ventilation pipe 43 5 7 Closing the cover 43 5 8 Provision for emergency drainage 44 5 9 Non return valve 44 5 10 Interception ga...

Страница 3: ...pliance by a person responsable for their safety Children should be supervised to ensure that they do not play with the appliance 1 3 Check that the system has suffered no damage during transport or s...

Страница 4: ...he level of the sewer network In compliance with the accident prevention regulations in force the FEKABOX FEKAFOS cannot be used for conveying inflammable or explosive liquids such as petrol diesel fu...

Страница 5: ...4 1 Dimensions and weights The adhesive label on the package indicates the total weight of the system The dimensions below are given in millimetres Only for Fekabox 200 Fekafos 280 280 Double Fekafos...

Страница 6: ...se the surface on which it is laid must be perfectly horizontal and it must be ensured that the whole bottom of the tank is in contact with the surface For Fekabox 200 l Fekabox 280 and Fekabox 550 Do...

Страница 7: ...rked with the symbol Make a hole in the tank in the determined areas indicated by the symbols shown above To make the hole use a hollow cutter as shown in figure 5 indicative figure with the correct d...

Страница 8: ...gases cannot get into other places such as buildings rooms and similar Avoid horizontal stretches in the ventilation duct 5 7 Closing the cover Check that the gasket of the cover is lying in the botto...

Страница 9: ...public private sewer network This will avoid the reflux of liquid Place the valve at a distance of at least 1 metre from the lifting station to allow the flow of liquid moved by the pump to open the s...

Страница 10: ...therefore intended for only one automatic single phase pump with float 20Kg A Remove the tank cover B Extract the slide 3 from the coupling foot 5 C For FEKA 600 screw the special 2 F 1 1 4 M couplin...

Страница 11: ...ENGLISH 46 FEKABOX 200 l PREPARED FOR THE FOLLOWING PUMPS FEKABOX 200 FEKA 600 MA FEKA VS VX 550 MA FEKA VS VX 750 MA FEKA VS VX 1000 MA FEKA VS VX 1200 MA FEKA VS Fig 8A Fig 8B FEKA 600 Fig 8 FEKA VX...

Страница 12: ...the top screw from the flange on the delivery side 1 Assemble the anti rotation bracket 2 Replace the screw 1 Extract the slide from the coupling foot 5 and connect it to the delivery port of the pump...

Страница 13: ...R 1800 T GRINDER 1000 1200 1600 MNA TNA FEKA 2015 2 MNA TNA 2025 2 2030 2 TNA PREPARED FOR THE FOLLOWING PUMPS FEKAFOS 280 DOUBLE FEKA VS VX 550 MNA TNA FEKA VS VX 750 MNA TNA FEKA VS VX 1000 MNA TNA...

Страница 14: ...OS 550 DOUBLE FEKA VS VX 550 MNA TNA FEKA VS VX 750 MNA TNA FEKA VS VX 1000 MNA TNA FEKA VS VX 1200 MNA TNA FEKA GRINDER 1400 M FEKA GRINDER 1800 T GRINDER 1000 1200 1600 MNA TNA FEKA 2015 2 MNA TNA 2...

Страница 15: ...he Dab Assistance Service for the commissioning of the system For connecting the system it is recommended to use exclusively the panels ED E BOX indicated by the manufacturer supplied complete with de...

Страница 16: ...n the ring nut and connect the cable to the control panel as indicated in the respective manual taking care that the terminals on the panel correspond to the respective float cables TWO FLOATS THREE F...

Страница 17: ...to check the operation of the alarm system Make a test of the complete system with clean water checking that the alarm system intervenes only in the case of a pump malfunction or lack of power in the...

Страница 18: ...ck that the system is working correctly and put it into service Close the cover or covers of the station screwing them into place If necessary fix the cover in its seat in such a way as to prevent una...

Страница 19: ...e grille is blocked G The impeller is worn or blocked by foreign bodies A Remove the obstructions B Check that the pump slide is at its full limit only for 280 l tanks C Clean the valve D Open the val...