Array mounting of groups of 4 units on a flatbed dolly
Groups of to 4 or 6 units are easy to transport by truck.
We will see in this section the assembly of an array system with groups of four units previously placed
on the PL-EV26S dollies.
The first group with 4 units will be the superior
group, that is to say, the group where we will install
the AX-EV26.
To assembly the AX-EV26, first, remove the
cover from the stack and use the pins of the top
cabinet.
Insert the pins of the top cabinet in the dedicated
holes of the AX-EV26, as shown in the figure 8 (3
pins are needed).
Next step would be running an Ease Focus
simulation in order to know the different splay
angles between the units and the pick up position.
(pin point of the central bar).
Before attaching the chain hoist to the AX-EV26,
the user should be able to vary the splay angles
between units and modify them accordingly to the
Ease Focus 3 simulation.
Warning: Verify the correct installation of
the security pins. These pins will support the
inferior load.
Fig.8
Fix the shackle in the pin point hole of the AX-EV26
determinated by the Ease Focus 3 project and
remove the pins that attach the bottom cabinet to
the dolly before lifting the system.
Set the splay angles between the units
accordingly to the Ease Focus Project. In this
case 0º, 2º and 4º.
Fig.9
set splay angles
remove pins