9 | Placement in service
58 / 88
Operating instructions CMVpro 125-400 ATEX | Version 1-en
At the end of the test run:
• Compare current values and parameters with initial values and parameters
from the beginning of the test run:
• Irregular running, vibration, or noises.
• Current draw of the electric motor.
• Vibration measurement.
• Check leak tightness of the sleeves.
• Measure temperature of the electric motor and compare with information in
the technical data sheet or on the nameplate.
• Create a test report during initial commissioning.
• The initial commissioning of the fan must also be documented with an ATEX
test report
_
82]. Either deliver the completed ATEX test re-
port to the operator or keep it with the project documents.