6 - START-UP
PRELIMINARY CHECKS
To check
before
starting-up the unit .
For details refer to the different manual sections.
√
Preliminary checks - Unit OFF power supply
Access in safety
Functional clearances
Structure integrity
Unit on vibration isolators
Unit input water shut-off valves for cleaning
Vibration isolators on water connections
Expansion tank (indicative volume = 5% system content)
Cleaned system
Loaded possibile glicole so corrosion inhibitor
Under pressure system
Vented system
Refrigerant circuit visual check
Earthing connection
Power supply features
Electrical connections provided by the customer
Outside air temperature probe
Содержание WSH 100D
Страница 9: ...9 4 WATER CONNECTIONS...
Страница 12: ...12 WATER CONNECTIONS...
Страница 14: ...14 5 ELECTRICAL CONNECTIONS 5 6 CONNECTIONS PERFORMER BY CUSTOMER...
Страница 15: ...15 5 ELECTRICAL CONNECTIONS...
Страница 16: ...16 5 ELECTRICAL CONNECTIONS...
Страница 31: ...31 8 MAINTENANCE...
Страница 46: ...46 NOTE...
Страница 47: ...47...