17
VCP-LTE will report according the group numeric order from the first programmed
Group to the last programmed group. This report sequence is one reporting cycle.
Reporting cycle is regarded as successful if any Group is successful, but VCP-LTE
will terminate reporting only after completing the reporting cycle (going from the first
programmed group to the last programmed group).
Reporting behavior depends on the event type:
Emergency
Events
:
-
When reporting to the first group is successful, Reporting is regarded as
successful. VCP-LTE will still report to the next group until all groups
have been tried to complete the reporting cycle.
For example, Groups 1 and 3 are assigned to Emergency Events:
If Group 1 is successful, VCP-LTE will still report to Group 3.
If reporting to Group 3 is successful, VCP-LTE will terminate reporting.
If reporting to Group 3 is unsuccessful (going through all the Report Index
within the group for 4 tries), VCP-LTE will also terminate reporting.
-
When reporting to the first group failed (going through all the Report
Index within the group for 4 tries), VCP-LTE will start reporting to the next
group. When reporting to the second group succeeds, reporting is
regarded as successful. If no other group is programmed, VCP-LTE will
stop reporting. If there are more groups programmed, VCP-LTE will
continue reporting until all groups have been tried to complete the
reporting cycle.
-
If reporting to all the programmed groups failed in a reporting cycle,
VCP-LTE will wait for 5 minutes. After 5 minutes, VCP-LTE will retry as it
starts another reporting cycle.
-
For Emergency event, VCP-LTE will repeat a reporting cycle for up to 3
times, with a 5-minute pause between each cycle, and then terminate
reporting.
Example 1, if Groups 1 and 3 are programmed for
“Emergency” reports, and
assuming NO successful report:
Group 1 > Group 3 > Wait 5 minutes > Group 1 > Group 3 > Wait 5 minutes >
Group 1 > Group 3 > Stops reporting.
Example 2, if Groups 1 and 3 are programmed for
“Emergency” reports, and
assuming NO successful report until Group 1 is successful after several
retries:
Group 1 > Group 3 > Wait 5 minutes > Group 1 > Group 3 > Wait 5 minutes >
Group 1 (Success!) > Group 3 > Stops reporting whether Group 3
succeeded or not.
Status Events
:
VCP-LTE will only go through one reporting cycle for Status reports.