Unit Installation
Figure 8: Gasket Installation Between Modules
Figure 7: Header Insulation
Front
Back
Grooved Couplings Installation
Inspect the pipe ends to ensure they are free from any
indentations, projections, roll marks, or other harmful
surface defects such as loose paint, scale, dirt, chips,
grease and rust . Inspect the grooved coupling gasket for
any defects . Grooved couplings are used to adjoin a bank
of modules . This requires the temporary removal of all
top, back and side sheet metal panels to obtain additional
access to the headers. With the first unit positioned, the
couplings can be installed using the following recommended
instructions:
Figure 9 - UCW/H Side View
3
1
2
4
Figure 10
Figure 11
• Remove the rubber gasket from the coupling .
• Apply a thin layer of silicone or other non-petroleum
lubricant to both the inner and outer surface of the
gasket to reduce friction .
• Slide the gaskets on the headers as shown in Figure 10 .
• Be sure the gasket is completely on the pipe to
eliminate any damage to the gasket .
• With gasket in place on each header of the positioned
unit (see Figure 11), move the second module into
position and line up the piping . Ensure alignment is
maintained for any additional modules to be added .
Sound Attenuation Panels and Gasket
Attenuation panels are enclosures made of 18 gauge
galvanized steel with powder coat paint finish and fiberglass
insulation. Panel package includes one (1) upper panel
made out of four (4) sections and one (1) lower panel for
each side of bank (field installed), four (4) panels for each
module in the bank (factory installed) and gasket sealant tape
for installation between modules . Install panels by setting
in place and locking down with the half turn latches or
self tapping screws .
Note: Panel package includes a
compressed 1” x 1” gasket sealant tape for installation
between modules
.
Install the tape on the outer frame
on the side of one module prior to installing the adjacent
modules. See Figure 8.
• Review Figure 9, UCW/H Side View below .
• Headers are numbered indicating the easiest order of
coupling installation .
• UCW/H chillers should have couplings installed on
headers 1, 4 from the top and 2, 3 from the
back of the unit .
Содержание UCH 30
Страница 16: ... www climacoolcorp com 14 Voltage Phase Monitor Wiring ...
Страница 21: ...19 www climacoolcorp com Figure 23 Part Load Performance Advantage ...
Страница 57: ...55 www climacoolcorp com Wiring Diagrams 030 050 070 Cooling Only ...
Страница 58: ... www climacoolcorp com 56 Wiring Diagrams 030 050 070 Cooling Only ...
Страница 59: ...57 www climacoolcorp com Wiring Diagrams 030 050 070 Heat Pump ...
Страница 60: ... www climacoolcorp com 58 Wiring Diagrams 030 050 070 Heat Pump ...
Страница 61: ...59 www climacoolcorp com Wiring Diagrams 085 Cooling Only ...
Страница 62: ... www climacoolcorp com 60 Wiring Diagrams 085 Cooling Only ...
Страница 63: ...61 www climacoolcorp com Wiring Diagrams 085 Heat Pump ...
Страница 64: ... www climacoolcorp com 62 Wiring Diagrams 085 Heat Pump ...
Страница 65: ...63 www climacoolcorp com Wiring Diagrams Master Panel ...
Страница 66: ... www climacoolcorp com 64 Wiring Diagrams Master Panel ...
Страница 70: ... www climacoolcorp com 68 Notes ...
Страница 71: ...69 www climacoolcorp com Notes ...