5 Assembly wall panels
Figure 12
Cement between casing
and panel
4-5 self-tapping screws spread
over the length
Cement between
The following activities are not applicable in situations where no top bar is assembled above the door.
9)
From the interior of the cabin measure the height between the top of the door frame and roof flange and mark this off
on a (residual) piece of wall panel.
Apply polymer cement as described (fig.12) and fasten the panel using 4-5 self-tapping screws.
The gap between casing and roof must be as small as possible.
10)
Seal all seams with polymer cement: between roof and wall panels, between seats and wall panels, between door
frame and wall panel.
Tip! Use a plastic spoon or a wiper together with a smoothing tool as usually described on the cement
packaging to finish the seams smooth and even.
SEDNA LINE 2008/05
25