Installation Instruction
Note: The Universal Clamp can be used both as a End Clamp and a Inter Clamp, and the height
can be adjusted from 30 to 46 mm.
When the side of the Universal Clamp close the narrow side of the Universal Clamp Buckle, it can be
used as End Clamp, and when the side of the Universal Clamp close the wide side of the Universal
Clamp Buckle, it can be used as Inter Clamp, as shown in the figure below.The Universal Clamp can
be directly rotated to the position of required End or Inter Clamp.
Recommended torque for M8 bolts when it is Inter Clamp is 18~20 N·m.
Recommended torque for M8 bolts when it is End Clamp is 13~14 N·m.
Inter clamp
90°
End clamp
4.6.2 Apply one pre-assembled Grounding Lug per Rail. Click the Grounding Lug into to the rail
channel and insert the Copper Wire. (the maximum size is 4 mm
2
or similar) Fasten the bolt M6*14 with
5~6 N·m and the bolt M8*25 with 16~20 N.m .Copper Pipe will be supplied for the case that using