![Clenergy PV-ezRack ezShade 2.0 Скачать руководство пользователя страница 8](http://html1.mh-extra.com/html/clenergy/pv-ezrack-ezshade-2-0/pv-ezrack-ezshade-2-0_installation-manual_2622550008.webp)
成Installation Guide_PV-ezRack_ezShade 2.0_AU_V1.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
13
page
of 19
成Installation Guide_PV-ezRack_ezShade 2.0_AU_V1.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
12
page
of 19
Installation Instruction
Installation Instruction
5.1.5
After placing an array support. Measure whether
all the end faces and top surfaces are on the same
plane and whether the installation angle meets the
requirements. as Shown in Figure 9.
Adjust the slot holes of T-base to meet the
requirements if there is deviation.
The adjustment range of the slot hole of T-Base as
shown in Figure 10.
Fasten all bolts after adjustment.
Recommended torque for M16 bolts is 100-105 N·m,
M20 is 200-220 N·m.
Figure. 9
Figure. 12
5.2 Rail 168 Installation
5.2.1 In order to form a longer section, first insert Splice halfway into end of T-Rail 168, and fasten by self-drilling
screws as shown in Figure 11.
5.2.1
Note: The position of self drilling screw ST6.3*22 for
connection as shown in Figure 12(unit:mm), total
16pcs on both sides. Tighten until the plastic pads
are slightly compressed.
5.2.2
Place one T-Rail 168 on Girder as shown in Figure 13.
Apply Rail Clamp to fix the T-Rail on Girder and fasten it by Allen Key.
Note: Apply two Rail Clamps for T-Rail on each side as shown in Figure 13
Recommended torque for M8 bolts is 18-20 N·m
Figure. 13
Figure. 11
Figure. 10
Adjust range:±20mm
Adjust range:±10mm