11
Revision date: 07.03.14
CLEARSPAN
™
PREMIUM MOO-TELS
2. Secure the leg pipes to the ground posts using the
5/16" x 2 1/2" machine bolts and nuts.
Rafter shown differs in design from actual rafter.
3. Use rope or cable to brace the rafter in position.
4. Carefully stand the first interior rafter, slide a band
clamp onto each rafter leg, position in place, and
secure the leg pipes to the ground posts.
Rafter shown differs in design from actual rafter.
1st Interior Rafter
End Rafter
FRAME ASSEMBLY (continued)
5. As the second rafter is steadied, remove one section of
pipe from one assembled purlin.
NOTE:
Work from the end of the purlin where the
first measurement was taken during the pre-marking
procedure, if used.
6. Insert the purlin pipe through the upper end clamp of
the end rafter and through a cross connector placed in
the same position on the
interior rafter.
7. Align the plain end of the purlin with the center of the
end rafter and rotate the purlin pipe so that the first
mark is visible (near the clamp of the interior rafter).
8. Tighten the end clamp and secure it to the rafter with a
Tek screw.
9. Install Tek screw through end clamp and into the purlin
pipe.
Purlin
End Rafter
Interior
Rafter
End Rafter
Do not allow the
purlin to extend
beyond the end
rafter
.
End rafter view
Interior rafter view
Inside of
Shelter
Outside of
Shelter
Rafter
Ground
Post
Band