![ClearSpan Premium Moo-Tel CD Скачать руководство пользователя страница 10](http://html.mh-extra.com/html/clearspan/premium-moo-tel-cd/premium-moo-tel-cd_assembly-manual_2621766010.webp)
10
Revision date: 07.03.14
CLEARSPAN
™
PREMIUM MOO-TELS
FRAME ASSEMBLY
After all ground posts are driven in place and rafters are
assembled, assemble the frame.
ASSEMBLE AND PRE-MARK THE PURLINS
The following steps describe one way to speed the
assembly process and eliminate the need to measure each
purlin as it is installed. Pre-marking the purlins ensures that
an accurate spacing of the rafter assemblies is achieved
and maintained during assembly.
Gather the Parts:
• Pipe 1.315'' x 75'' swaged (#131S075)
• Pipe 1.315'' x XX'' plain (#131P0XX)
• Marker and tape measure
NOTE:
The purlins are part of the assembled frame and
run perpendicular to the rafter assemblies. Each purlin
consists of 1.315" x 75" (#131S075) swaged pipes (number
is determined by shelter length) and one (1) 1.315" x XX"
(#131P0XX) plain pipe.
ATTENTION:
The XX" represents the remaining length
required to reach the end of the shelter. Consult the Spec
Sheet for part identification.
1. Select the required pipe sections for one purlin and
connect these by inserting the swaged ends of the
pipes into the plain ends until the entire purlin is
assembled.
NOTE:
Assemble the purlins in a location that is
accessible during the assembly of the frame, but will
not interfere with the process of lifting and setting the
rafters.
2. Verify that each pipe joint is properly seated.
NOTE:
These pipes must be separated during the
assembly procedure. Do not fasten them together at
this time.
3. For the 48" rafter spacing, measure forty-eight and
three-quarters inches (48-3/4") from one end of the
assembled purlin and mark the distance on the pipe.
NOTE:
This first measurement is three-quarters (3/4)
of an inch longer than the on-center rafter spacing
to account for the length of purlin pipe that extends
through the end purlin clamp of the first end rafter.
4. From the location marked in the previous step,
measure forty-eight inches (48") and make another
mark on the assembled purlin.
5. Continue to mark the purlin in 48" intervals until all
locations are marked. These marks help to maintain
the 48" on-center rafter spacing of the shelter during
assembly.
6. Repeat this procedure until all assembled purlins are
marked.
7. After assembling all rafters and pre-marking the purlins,
assemble the frame.
ASSEMBLE THE FRAME
After all ground posts are driven in place, rafters are
assembled and purlins pre-marked, assemble the frame.
Gather the parts:
• All rafter assemblies and pre-marked purlins
• Band clamps (#QH1402)
• Cross connectors (#102548)
• 5/16" x 2-1/2" machine bolts and 5/16" nuts
• Lifts, ladders, and assistants
• Rope or cable
1. Carefully stand the
first end rafter
, slide a band clamp
onto each rafter leg, and place the leg pipes in the first
set of ground posts.
Brace the rafter in place to keep it straight. Depending
on the frame size, a lift and additional assistants may
be needed. Consult Quick Start section for details.
Rafter shown differs in design.
ATTENTION:
Stand the rafter so the nuts and bolts of
the end clamps are to the inside of the frame.