24
Revision date: 07.03.14
CLEARSPAN
™
PREMIUM MOO-TELS
INSTALL THE DROP-DOWN CURTAIN (continued)
10. Carefully lift the assembly and insert the tapered/free
end of the 131S075 pipe through the 2" axle conduit
hole, or 'X', in the end panel.
11. Align the plate mounting holes with the mounting
holes drilled in the end rafter (Step 3) and reattach the
mounting plate using two 1/4" x 4" carriage bolts, 1/4"
lock nuts, and 1/4" flat washers.
NOTE:
Cover is not shown in the above diagram.
Diagram shows gearbox mounted to the end rafter on
the outside of the end wall cover.
12. Move inside the frame and slide a 106734 band clamp
over the tapered end of the 131S075 pipe.
Axle Conduit
106734 Band
Clamp
Gearbox bolted
to end rafter.
2" Axle
Conduit
Hole
or 'X'
End Panel
Frame shown may differ from actual shelter.
Axle Conduit
13. Verify that the pipe is level and secure the band clamp
to the underside of the second rafter using an FA4484
Tek screw. Pipe should remain loose in the band clamp.
Band clamps support the axle conduit at each rafter
except the end rafter where the gearbox is mounted.
14. Take a section of 131S075 pipe, attach it to the first,
and secure the connection using one Tek screw.
15. Slide another band clamp onto the tapered/swaged end
of the conduit, level the conduit, and secure the band
clamp to the underside of the next rafter.
16. Continue adding conduit and band clamps and work
toward the other end of the shelter. Verify that the axle
conduit remains level throughout the length.
Attach one
band clamp to the inside of each rafter.
17. Select the final section of plain pipe (131P0XX where
XX represents the length needed to reach the end of
your building. Consult side profile diagram for pipe
identification.)
Interior Rafter
Axle Conduit
106734 Band
Clamp
As seen from
the inside.
Photo shows the
fully assembled
drop-down
curtain from
the inside of a
sample shelter.
Curtain is
installed later.
Axle Conduit
Ribbon Board
As seen from
the inside.
Band Clamp