System Hardware Best Practices
System Hardware Best Practices
Use the recommendations in this section to ensure the proper installation, initialization, and operation
of the system. This section includes the following topics:
•
Installation Best Practices, page D-2
•
Initialization Best Practices, page D-2
•
System Operation Best Practices, page D-2
Installation Best Practices
When installing the chassis, follow these best practices:
•
Plan your site configuration and prepare the site before installing the chassis.
•
Verify that you have the appropriate power supplies for your chassis configuration.
•
Install the chassis following the rack and airflow guidelines presented in this guide.
•
Verify that the chassis is adequately grounded.
Initialization Best Practices
When the initial system boot is complete, verify the following:
•
Power supplies are supplying power to the system.
•
Fan modules are operating normally.
•
The system software boots successfully. See the
Cisco UCS Manager CLI Configuration Guide
appropriate to your software version.
System Operation Best Practices
To ensure proper operation of your system, take the following actions:
•
Make a copy of the running configuration to CompactFlash for a safe backup.
•
Never use the
init system
CLI command unless you understand that you will lose the running and