6.3.- START-UP  

1.-  Connect  the  measuring  cables  (2)  and  the  current  injection  cables  (3),  depending  on  the 
measurement you are going to take. 
2.-  Connect  the  power  supply  cable  (7)  to  the  MPC  and  to  the  mains  socket.  The  device  is 
designed  to  operate  with  230  Vac.  50/60  Hz.  Please  ensure  that  the  voltage  is  correct  before 
plugging in the device. The device is protected from overvoltage with a F250 mA fuse 
 
Note: 
Connect the device to a line or generator capable of supplying the required power: 
 

Required power 

 (600 V x current to be injected) 

 

3.- Flip the switch (6). The red LED will light up. 
 
 
 
 
 
 
 
 
4.- Before connecting the telephone and unit via Bluetooth, we first have to link the Getest unit to 
the telephone as follows: 
 
Touch the following icon on the phone's main screen which will take you to settings 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
5.-  Select  the  "Wireless  connections"  option.  Activate  Bluetooth  and  then  click  on  the  "Scan  for 
Devices"  option.  The  telephone  will  detect  the  switched-on  Getest  unit  with  the  name 
ESD100v1.1.0. Click on that name and wait for the blue "Linked" message to appear.  
 
  
 
 

Содержание Getest

Страница 1: ...INSTRUCTION MANUAL M98224701 03 13A...

Страница 2: ...has the skills and knowledge related to the construction and operation of the electrical equipment and installations and who has received safety training on the hazards involved WARNING Consult the i...

Страница 3: ...as a cabo exclusivamente por pessoal qualificado O C digo El ctrico Nacional define uma pessoa qualificada como uma pessoa que se encontre familiarizada com a constru o e opera o do equipamento assim...

Страница 4: ...______________________________________________ 9 5 1 PERFORMANCE FEATURES ________________________________________________________9 5 2 ELECTRICAL FEATURES ____________________________________________...

Страница 5: ...the unit throughout its working life In particular follow the installation standards indicated in the Low Voltage Directive and additional technical instructions The installation operation and mainte...

Страница 6: ...he instrument has two ergonomic handles and we recommend it be carried by two people The device also includes two electrodes These weigh 25 kg each This weight may be harmful if it is not lifted If th...

Страница 7: ...libration certificate Samsung Galaxy Young telephone with all its components charger box etc Cocodrile clamp Cable to connect the weights Measuring pick 2 switches Instruction Manual If any problem is...

Страница 8: ...The centre of gravity of some units may be found at a considerable height Therefore when handling with a forklift it is recommended that the unit be securely fastened and that no abrupt operations are...

Страница 9: ...ications to the device or the unit specifications set out in this instruction manual without prior notice CIRCUTOR SA advises the user to obtain the device s latest version of the specifications and a...

Страница 10: ...nt 15 Aac You need a low impedance power supply line to get maximum performance given that peaks of up to 130 A for 20 ms may appear when applying maximum power We recommend using cable with a cross s...

Страница 11: ...Compliance The device complies with EU directives LVD 2006 95 EC and EMC 89 336 EEC Due to the nature of the device an injection of several amps will cause some disturbances in the power supply lines...

Страница 12: ...nical service representative 6 1 INSTALLATION The Getest may be powered directly from the mains 230 Vac and 50 60 Hz or from a single phase generator set The required power of the generator set will d...

Страница 13: ...to perform the test as well as the current and voltage coils supplied with the unit 6 2 UNIT PARTS GETEST Wiring Max R 5A Max R 10A Max R 25A Max R 50A Power on indicator Safety switch 20 A D curve c...

Страница 14: ...GETEST Page 14 of 24 PDA Android PDA Windows Mobile...

Страница 15: ...the device to a line or generator capable of supplying the required power Required power 600 V x current to be injected 3 Flip the switch 6 The red LED will light up 4 Before connecting the telephone...

Страница 16: ...switch 5 to the Enabled position 9 Select the testing mode resistance step or contact If you select resistance you must indicate the test current In step and contact mode you must indicate the maximu...

Страница 17: ...nal b Current output contactor connection c Erratic voltage measurement d Test at 25 Vac e Injection of as a minimum the required current f Increased voltage if the desired current is not reached g In...

Страница 18: ...t must not exceed 10 Hardware earthing detail You must find or build a good auxiliary earthing as it will determine whether the unit can inject the test current Bearing in mind that the ohmic value of...

Страница 19: ...yellow green to the Getest s voltage terminals yellow green Run the other end to the weights one cable for each weight Arrange the weights one metre apart from each other simulating the passage of a p...

Страница 20: ...or substation Once the connections are made select step voltage mode in the PDA and enter the maximum fault current value provided by the supply company 7 2 CONTACT VOLTAGE To perform the contact test...

Страница 21: ...contact or resistance the auxiliary earth must be good enough to allow a correct measurement Bear in mind that a poor auxiliary earth adds a series resistance to the circuit which reduces the MPC dev...

Страница 22: ...oid version 1 Connect your telephone to the computer with a USB cable 2 Enable the phone s connection to the computer 2 Enter in My PC and select the Removable device icon 3 Open the desired file 9 WA...

Страница 23: ...ontinue There is a risk of electric shock The loop resistance is too high for the requested current MPC will apply the maximum power but will not be able to reach the required value Error impossible t...

Страница 24: ...to LV Regulations or that surpasses the limits indicated in the technical and environmental features of this manual In particular capacitor units are very sensitive to adverse environmental condition...

Отзывы: