5  Commissioning of the System

The commissioning of a photovoltaic system is part of the 

proper and professional implementation and installation. It 

must only be performed following a careful visual examina-

tion and a professional electrical inspection. Furthermore, 

a report of the commissioning must be prepared. 
Follow  the  below  checklist  during  commissioning  of  the 

system.

Visual examination:

P

P

Anchoring of the components to the roof structure

P

P

Fastening  of  the  module  according  to  the  laying 

guidelines

P

P

Cable installation on modules, generator connection 

boxes, DC-sectioning points and inverters

P

P

Potential equalization (if applicable)

Electrical inspection

P

P

String open circuit voltages

P

P

String open circuit currents (use load break switch)

P

P

PV generator open circuit voltage

P

P

Voltage  drop  on  fuses  (for  PV  systems  with  string 

fuses)

P

P

Insulation resistance of the PV generator

P

P

Insulation resistance of the DC main lead

P

P

Insulation resistance of the AC lead

P

P

Loop resistance of the AC circuit

Report:

P

P

Name of the system operator

P

P

Location of the system

P

P

Specifications of the photovoltaic system

P

P

Results of the visual examination

P

P

Results of the electrical inspection

P

P

Confirmation of completion by signature of the installer 

Please note:

This  list  is  only  for  your  information.  It  does  not  raise  a 
claim on completeness.

6  Maintenance and cleaning

This photovoltaic system requires extremely little mainte-

nance and servicing. 

However, do inspect the system regularly and perform 

a check every 6 months following this scheme:

P

P

Checking of the solar modules for scratches, optical 

changes or contamination

P

P

Checking  of  the  module  fastening  (tightness  of  the 

welding seams, strength of the butyl bondings, loos-

ening of screws) 

P

P

Checking of the wiring as far as accessible (connect-

ing lead, fastenings, mechanical damages)

P

P

Checking of the roof tightness 

P

P

Checking of the electrical functions of all components

P

P

Monitoring of the operational safety of the electrical 

components 

This  list  is  only  for  your  information.  It  does  not  raise  a 

claim on completeness. 

Caution! 

No high pressure cleaning!

Usually,  the  modules  are  automatically  cleaned  by  rain. 

With an inclination of more than 15° the modules generally 

need no additional cleaning. In case the module surface 

is contaminated by leaves, bird feces, pollen etc. we rec-

ommend cleaning with sufficient water without detergents. 

The modules are best cleaned using a water hose and soft, 

gentle cleaning equipment, e.g. a sponge or a car clean-

ing brush. To avoid micro-scratches, which may affect the 

yield of the system or could lead to module damage in the 

long run, the dirt must never be rubbed or scraped off the 

surface in a dry state.

11

Installation Guide

Содержание TFP 288 Professional

Страница 1: ...Installation Guide www centrosolar com TF Plate Professional Installation Guide TFP 288 Professional...

Страница 2: ......

Страница 3: ...1 About this guide 2 2 Site preparation 2 3 Installation prerequisites 3 4 Safe Installation 4 5 Commissioning of the System 9 6 Maintenance and cleaning 9 7 Technical Specifications 10 8 Warranty and...

Страница 4: ...bilities 2 Site preparation The TF Plate Professional modules are sensitive techni cal components which must be handled with utmost care Pay special attention during transport or when putting into int...

Страница 5: ...with the modules only use original MC3 plugs by Multi Contact or LC3 plugs by Lumberg P P If more than three strings are to be connected to the inverter in parallel use a DC Connect junction box to e...

Страница 6: ...alled at the bottom of the inclination green 4 Safe Installation Distance between high beading and lining The free distance between the high beadings of the trap ezoidal sheet metal and the lining of...

Страница 7: ...mm x 50 mm and bonded to the trap ezoidal metal sheet at all screwing positions Figure 9 If the TF Plate Professional is laid with adjoining long sides the joint area of the two modules must be sealed...

Страница 8: ...utyl strip is not necessary Caution Fasten screws properly Ensure a good screw connection of the module located at the end stops at all predetermined points All screws must be tightened with a tighten...

Страница 9: ...cable duct Apply an approx 6 mm wide strip of MS polymer adhesive with a 15 mm distance to the edge of the module carrier plate The adhesive strip should begin with an approx dis tance of 25 mm to the...

Страница 10: ...rier plate 1a on the front side with equal lateral distances 3 Cable duct cover plate l 3000 mm b 160 mm screwed to cable duct base plate and clamped to fastening buttstrap 4 4 Fastening buttstrap l 2...

Страница 11: ...lease note This list is only for your information It does not raise a claim on completeness 6 Maintenance and cleaning This photovoltaic system requires extremely little mainte nance and servicing How...

Страница 12: ...attern diagonal laying mm Quality Features Performance tolerance 5 Power output warranty 10 years at 92 nominal output 20 years at 84 nominal output 25 years at 80 nominal output Product warranty 5 ye...

Страница 13: ...ts For more information about warranty and guarantee see the warranty statement of CENTROSOLAR AG under www centrosolar com 9 Disclaimer Photovoltaic systems consists of electrical and mechani cal com...

Страница 14: ...Installation Guide 14...

Страница 15: ......

Страница 16: ...a 08039 Barcelona SPAIN Tel 34 93 3435048 info espana centrosolar com CENTROSOLAR FRANCE SARL Espace Europ en 15 chemin du Saquin Batiment G 69130 Ecully FRANCE Tel 33 4 69848210 info france centrosol...

Отзывы: