PG 5
DOVER FLOOR
-
OPTIONAL
Step 1: Lay out floor joists, and assemble sub floor as shown below, nailing sub
floor together with 90mm nails. Ensure joists are level and supported every
800mm. Check diagonals before screwing 6 sheets of 17mm ply to frame using
40mm screws as shown.
Step 2: Nail plastic weather strip to edge of floor
on all four sides, with 30mm clouts, (approx 5
nails per side) ensuring top edge is flush with top
of floor. This isn't required if shed is on a concrete
base.