Start-up
36
VVT Zone Controller
Before starting the air source fan, make sure the zone terminal dampers are not closed. Starting the fan
with dampers closed will damage the system ductwork.
Commissioning the VVT Zone Controller
Using Field Assistant or i-Vu:
1
Calibrate the damper travel.
a)
Go to
Properties
>
Configuration
>
Service Configuration
>
Pressure Dependent Control
>
Details
tab >
Test and Balance
. Click
Calibrated Damper Close
b)
Click
and verify it goes to the closed position.
Calibrated Damper Open
c)
Click
and verify it travels to the full open.
Automatic Control
2
For Parallel or Series Fan terminals – in the
Locks
section, select the
Fan
's
Lock value to
checkbox, then
select
On
in the droplist. Click
Apply
. Verify the fan's operation.
to return the damper to normal operation.
3
For modulating hot water reheat – Go to
Properties
>
I/O Points
tab, then lock
Hot Water Valve
to 100%.
If the controller is configured for Single Duct, make sure the air source fan is on. If ducted heat, verify the
heat works by verifying that the SAT rises. For baseboard heat, physically check the heating element for
proper temperature rise. Release the
Hot Water Valve
.
4
Release the fan.
5
If the controller is part of a linked system, verify
Linkage
>
Airside Linkage Status
shows
Active
.
CAUTION
Pressing the actuator release button and moving the damper or disconnecting the actuator ribbon
connector while the bypass controller is powered will cause the damper position to be out of calibration. To
recalibrate the damper position, you must perform steps 1a–1c above or power cycle the controller.
Balancing the system
Most VVT system airflow designs are based on cooling requirements which require a greater CFM flow than
heating requirements. Using this balancing procedure, you will adjust the cooling airflow first. If the heating
and cooling maximum airflow requirements are the same, you will not need to balance the heating airflow.
There are two methods of balancing the system. Using the Test & Balance program or using i-Vu/Field
Assistant. Test & Balance can perform all of the steps outlined here, including shutting down the Linked air
source and performing global commands to all zones in the system. Items 1 through 5 in Step 1 should be
done prior to using Test & Balance. Please refer to Test & Balance's Help files for details on the required
steps to complete the balancing procedure.
Complete the following steps when using i-Vu or Field Assistant to perform the system balancing.
NOTE
We recommend that the heating minimum airflow settings for all the zones in the system be set to
maintain the air source’s design minimum heat CFM airflow across its heat exchanger to prevent damage to
the equipment.
Содержание OPN-VVTZC
Страница 2: ......
Страница 27: ...VVT Zone Controller 23 Single duct 2 position hot water Single duct modulating hot water...
Страница 29: ...VVT Zone Controller 25 Fan box 2 position hot water Fan box modulating hot water ducted or baseboard...
Страница 30: ...Installation 26 VVT Zone Controller Fan box combination baseboard and ducted heat Fan box 2 stage electric heat...
Страница 79: ......